BLD-Ceiling Grid Inspection | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PASS |
Mike Jordan
|
|
|
Call 30 min before Phone #: ###-#### Inspection requested via web by Clint Hogwood. All issues are resolved. Ok to place tile.
|
BLD-Ceiling Grid Inspection | 7/28/2020 | 7/29/2020 | 7/29/2020 | A | PASS |
Mike Jordan
|
|
|
Call 30 min before inspection please Phone #: ###-#### Inspection requested via web by Clint Hogwood. Ok to start installing ceiling tile. Needs to provide the spacers for rated light fixture overs.
|
BLD-Ceiling Grid Inspection | 7/15/2020 | 7/16/2020 | 7/16/2020 | A | NR |
Mike Jordan
|
|
|
Call 30 min before as I am not on site Phone #: ###-#### Inspection requested via web by Clint Hogwood. Needs to provide UL data sheets on how grid installs and data sheets for main tees and cross tees.
|
BLD-Ceiling Grid Inspection | 5/5/2020 | 5/6/2020 | 5/6/2020 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Hogwood. 2nd. floor rooms only ok.
|
BLD-Ceiling Grid Inspection | 4/30/2020 | 5/1/2020 | 5/1/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Hogwood. 1st. floor rooms only, o corridors at this time.
|
BLD-Ceiling Grid Inspection | 4/28/2020 | 4/29/2020 | 4/29/2020 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Hogwood. Provide UL listed 1 hr. ceiling grid system in 1hr. corridors. Also appears that doors and glazing have been switched out and ratings not maintained. Also noted several apeas were grid system is not completed. Correction notice was issued.
|
BLD-Framing/Rough-in | 10/30/2019 | 10/31/2019 | 10/31/2019 | A | PASS |
Mike Jordan
|
|
|
Call for access // Josh Phone #: ###-####. INterior steel stud framed wall ok.
|
BLD-Conference | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | DONE |
Mike Jordan
|
|
|
Josh Phone #: ###-####. A correction notice was issued to provide two wires on opposing sides to installed light fixtures in grid and attach to structure above.
|