BLD-Final | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Band
|
DOC - Permit Finaled | | | 10/21/2019 | | DONE |
|
|
|
Per passing BLD Final from 425 on 10/21/19
|
BLD-Final | 10/17/2019 | 10/17/2019 | 10/17/2019 | A | PART |
Mike Jordan
|
|
|
Needs to repair and provide an additional handrail on the ramp on the north west side of building. his ramp is not part of the accesible route or egress.
|
BLD-Final | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | NR |
Mike Jordan
|
|
|
T.I. contractor was told we needed a structural inspection w/ Dave Hannah We had a framing Inspection for shell in June or July, w/ Mike Jordan Phone #: ###-#### Inspection requested via web by Gary Band. Noted that zoning final failed back in July. Needs to resolve and get reinspection.
|
BLD-Conference | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | DONE |
Mike Jordan
|
|
|
T.I. contractor was told we needed a structural inspection w/ Dave Hannah We had a framing Inspection for shell in June or July, w/ Mike Jordan ??? Phone #: ###-#### Inspection requested via web by Gary Band
|
FIRE-Final Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm permit under tenant improvement permit, fire extinguishers provided by tenant improvement. Final life fire safety inspection for this scope of work complete.
Looking for Life, Fire, Safety Inspection so T.I. contractor can get his final. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Wall cover | 7/26/2019 | 7/29/2019 | 7/30/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Band covering int side of ext walls for shell and core
|
BLD-Framing/Rough-in | 7/13/2019 | 7/15/2019 | 7/15/2019 | A | PASS |
Dave Hannah
|
|
|
request is for a framing inspection of exterior soffit steel framing under the canopies. F/S ; elect inspections have been completed. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Wall cover | 6/28/2019 | 6/28/2019 | 6/28/2019 | A | CANC |
Mike Jordan
|
|
|
looking for insulation inspection - by offered listings, not sure if it''s this or "energy compliance" Thank you Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Energy code compliance | 6/28/2019 | 6/28/2019 | 6/28/2019 | A | PASS |
Mike Jordan
|
|
|
looking for insulation inspection - by offered listings, not sure if it''s this or "wall cover" Thank you Phone #: ###-#### Inspection requested via web by Gary Band
|
FIRE-Conference | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | CANC |
Jim Page
|
|
|
|
FIRE-Conference | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | DONE |
Jim Page
|
|
|
Gas meter is set in the wrong location, city approved drawings show gas meter by north door, currently meter is set under PIV for fire sprinklers, needs to be relocated to give the required 36 inch clearance around PIV.
|
BLD-Framing/Rough-in | 6/25/2019 | 6/26/2019 | 6/26/2019 | P | DONE |
Mike Jordan
|
|
|
Request for shell framing inspection - Phone #: ###-#### Inspection requested via web by Gary Band. Completed in the am.
|
BLD-Framing/Rough-in | 6/25/2019 | 6/26/2019 | 6/26/2019 | A | PASS |
Mike Jordan
|
|
|
Request for shell framing inspection - Phone #: ###-#### Inspection requested via web by Gary Band. Ok to insulate.
|
BLD-Wall Bracing | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Dave Hannah
|
|
|
request shear and roof nailing inspection Tuesday morning. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Foundation | 3/29/2019 | 4/2/2019 | 4/2/2019 | A | PASS |
Dave Hannah
|
|
|
stem wall forms / rebar inspection request MTI will also look at bar w/ concrete testing request late morning for 2:00 pm pour Best access @ E gate into project from W edge of parking lot Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Foundation | 3/29/2019 | 4/2/2019 | 4/2/2019 | P | CANC |
Dave Hannah
|
|
|
stem wall forms / rebar inspection request MTI will also look at bar w/ concrete testing request early afternoon insp for 2:00 pm pour Best access @ E gate into project from W edge of parking lot Thank you. Phone #: ###-#### >> Inspection requested via web by Gary Band Inspection cancelled from web by: Gary Band
|
BLD-Footing | 3/26/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Dave Hannah
|
|
|
Request footing inspection early afternoon for 2;00 pm pour. Corner of Capitol ; Broad. 390 S Capitol Blvd. just S of Trader Joes. Best access @ East site gate off W edge of TJ''s parking lot. Can temp park in gate opening. Thank you! Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Footing | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PEND |
Dave Hannah
|
|
|
Request footing inspection late morning for 2;00 pm pour. Corner of Capitol ; Broad. 390 S Capitol Blvd. just S of Trader Joes. Best access @ East site gate off W edge of TJ''s parking lot. Can temp park in gate opening. Thank you! Phone #: ###-#### Inspection requested via web by Gary Band ok after spec inspection is aproved
|