BLD-Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. OK for perm occ.
|
FIRE-Final Inspection | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####
|
BLD-Final | 6/12/2019 | 6/13/2019 | 6/13/2019 | P | PART |
Mike Jordan
|
|
|
David Phone #: ###-####**Originallly schedule for AM change to PM**. Ok for perm occ. only. Needs other trades to sign perm and need to inspect racking system once permit has been issued.
|
FIRE-Final Inspection | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PART |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers will be placed in discussed location. TCO is authorized contingent on the racking permit (BLD19-02023) getting inspected and passed. After racking permit is finaled then a final life fire safety inspection will be required to finalize inspection process for life safety.
David Phone #: ###-####
|
BLD-Final | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | NR |
Mike Jordan
|
|
|
David Phone #: ###-####
|
FIRE-Final Inspection | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the hardware for door 113 is addressed and the transfer grill is installed for the smoke evac system from the Mall space as per the approved plans. Still need racking permit inspected. I'm ok for product to be brought into the store but the racks can not be used until the racking permit is approved.
David Phone #: ###-####
|
BLD-Final | 6/6/2019 | 6/10/2019 | 6/10/2019 | P | NR |
Mike Jordan
|
|
|
David Phone #: ###-####
|
FIRE-Final Inspection | 6/6/2019 | 6/10/2019 | 6/10/2019 | A | FAIL |
Troy Cobbley
|
|
|
The only item ready for testing/inspection was the smoke evac system which functioned correctly.
David Phone #: ###-####
|
BLD-Framing/Rough-in | 5/29/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####. Interior steel stud framed walls and hardlids for restrooms ok.
|
BLD-Framing/Rough-in | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####. Interior steel stud framed walls only ok.
|
BLD-Framing/Rough-in | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####. INterior steel stud furred wall for panels.
|
BLD-Framing/Rough-in | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Mike Jordan
|
|
|
Taylor- demising wall inspection Phone #: ###-####. Interior steel stud framed demissing wall only ok to cover.
|
BLD-Framing/Rough-in | 4/15/2019 | 4/15/2019 | 4/16/2019 | P | FAIL |
Mike Jordan
|
|
|
framing insp. just for the demising wall // Taylor Phone #: ###-####. No city approved plans on site.
|