BLD-Wall Bracing | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | PART |
Dave Hannah
|
|
|
Screened- James Phone #: ###-#### ok to cover ext but shear panel on 7 line needs to be reengineered hold downs in wrong spots and window added.
|
BLD-Aging Inspection | 6/4/2020 | 6/4/2020 | 6/4/2020 | | DEFR |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | DONE |
Brandon Shaw
|
|
|
|
BLD-Foundation | 1/21/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Brandon Shaw
|
|
|
First floor slab and interior footings...
|
BLD-Footing | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | PASS |
Brandon Shaw
|
|
|
Mark Phone #: ###-####
|
BLD-Foundation | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 9/13/2019 | 9/16/2019 | 9/16/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 8/9/2019 | 8/12/2019 | 8/12/2019 | A | PART |
Brandon Shaw
|
|
|
Back East wall only....
|
BLD-Footing | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | PASS |
Brandon Shaw
|
|
|
Entire residence and pool footings... Work in progress...
|
BLD-Footing | 7/25/2019 | 7/25/2019 | 7/25/2019 | P | NR |
Brandon Shaw
|
|
|
Need soil subgrade submitted and approved by PW...
|
BLD-Footing | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | NR |
Brandon Shaw
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 7/19/2019 | 7/19/2019 | 7/19/2019 | P | NR |
Jim Storey
|
|
|
Wes Phone #: ###-#### A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|