BLD-Final | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Mike Jordan
|
|
|
Plumbing inspector signed off plumbing final. Ready to final. Phone #: ###-#### Inspection requested via web by Michael McHargue. OK for perm occ. Plumbing has signed perm.
|
BLD-Final | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PART |
Brandon Shaw
|
|
|
OK for temp CofO... Pending back flow cert. see PLM19-00890... No other issues...
|
FIRE-Final Inspection | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Adam Phone #: ###-####
|
BLD-Final | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | PASS |
Mike Jordan
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
BLD-Conference | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Joslin. All issues resolved. Ok for perm occ.
|
BLD-Ceiling Grid Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Joslin
|
BLD-Ceiling Grid Inspection | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | FAIL |
Mike Jordan
|
|
|
Fire Sprinkler Inspected scheduled for AM - likely to occur early morning. Ceiling Grid Inspection to follow - late morning if possible. Phone #: ###-#### Inspection requested via web by Adam Joslin. Remove all tile for inspection.
|
BLD-Ceiling Grid Inspection | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Joslin. Needs fire sprinkler rough in first.
|
BLD-Energy code compliance | 4/8/2019 | 4/10/2019 | 4/10/2019 | A | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 4/5/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Mike Jordan
|
|
|
Adam-late am if possible Phone #: ###-####. Interior wood framed walls ok.
|