BLD-Final | 9/20/2019 | 9/20/2019 | 9/20/2019 | P | PASS |
Brandon Shaw
|
|
|
Caleb- Phone #: ###-####
|
DOC - Permit Finaled | 9/20/2019 | 9/20/2019 | 9/20/2019 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, no fire sprinklers, no fire alarm modificaitons, fire extinguisher is placed with a current inspection tag, round type door hardware on breakroom door to be changed to lever type before building final, will be verified during final inspection. Final life fire safety inspection for area of work complete, signature card not provided, no signatures given.
Kaleb Phone #: ###-####
|
FIRE-Final Inspection | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | CANC |
Troy Cobbley
|
|
|
Could not make it to this inspection due to work load and time constriants. Will need to be rescheduled. Caleb Phone #: ###-####
|
BLD-Final | 8/25/2019 | 8/26/2019 | 8/29/2019 | A | CANC |
Dave Hannah
|
|
|
The building will be open after 9. Just ask for Becca. Thank you. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole
|
FIRE-Final Inspection | 8/27/2019 | 8/28/2019 | 8/28/2019 | A | FAIL |
Jim Page
|
|
|
Provide code compliant door hardware for breakroom door. Provide a fire extinguisher with a current ispection tag, current tag is from 1986. Thumbturn deadbolt on main entry needs to be changed to a double-key deadbolt and provide signage at main door reading "Door to remain unlocked while building is occupied".
The building will be open at 9. Ask for Becca at the front desk. She has the approved plans. Thank you. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole
|
FIRE-Final Inspection | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | FAIL |
Troy Cobbley
|
|
|
Left message on contacts voice mail that I was on the way. Got to project site but did not make contact with anyone except the owner. She did not have plans. No inspection performed. Jay Phone #: ###-####
|
BLD-Framing/Rough-in | 5/15/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Tony Young
|
|
|
Just inspection of the remaining rooms. Should be the front 2 rooms on the west side. The goal is to have the whole building approved for cover. Thank you. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole// ok after fixing the insulation
|
BLD-Framing/Rough-in | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PART |
Dave Hannah
|
|
|
Please give me a call. I would like an inspection on the rooms on the north side and the 3 rooms on the north west side, and the rooms in the center of the building. I have marked the plans with NO on the rooms that are not ready. The plans are on the table in the room on the south west corner of the building. Thank you. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole ok to cover rooms ok by elec
|
BLD-Framing/Rough-in | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PART |
Brandon Shaw
|
|
|
I need a rough in inspection on the east half of the building only. I'd like to hang sheet rock on that half only, so just an ok to cover the walls and ceiling on that half is the goal. OK to cover as requested...
|