BLD-Final | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by chad stradley. Per Jim Storey - TCO only - OK for Perm with ELE and Zoning Final
|
FIRE-Final Inspection | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed for building 5. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Framing/Rough-in | 6/2/2020 | 6/3/2020 | 6/3/2020 | P | PASS |
Jim Storey
|
|
|
Fire barrier wall sheet rock Inspection. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Framing/Rough-in | 5/18/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Jim Storey
|
|
|
for cover inspection. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Aging Inspection | 5/1/2020 | 5/1/2020 | 5/1/2020 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Footing | 12/16/2019 | 12/19/2019 | 12/19/2019 | P | PART |
Tell Riley
|
|
|
They will be pouring at 2 pm. Strata will be on site at 145 PM for testing Phone #: ###-#### Inspection requested via web by chad stradley//ok pend specials//cleaning footings to meet frost depth while onsite//blankets onsite//
|
BLD-Footing | 12/16/2019 | 12/18/2019 | 12/16/2019 | P | CANC |
Jim Storey
|
|
|
They are looking to pour footer at 2PM. Strata will be on site at 245PM. Thank you. Phone #: ###-#### >> Inspection requested via web by chad stradley Inspection cancelled from web by: chad stradley
|
BLD-Foundation | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Jim Storey
|
|
|
damp proofing on building retaining walls Phone #: ###-#### Inspection requested via web by chad stradley
|