BLD-Final | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Jim Storey
|
|
|
Plumbing backflow cert passed and all other inspections complete. Looking for final sign-off for full Occupancy Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
BLD-Final | 6/12/2019 | 6/12/2019 | 6/12/2019 | A | PART |
Brandon Shaw
|
|
|
See PLM19-01175- need back flow cert...
|
FIRE-Final Inspection | 6/6/2019 | 6/7/2019 | 6/7/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers will be placed in discussed locations and have current inspection tags. Final life fire safety inspection for area of work complete.
To coincide with Fire Alarm final for Johnson Controls/TYCO. Had a miscommunication in scheduling previously. Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
FIRE-Final Inspection | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | FAIL |
Jim Page
|
|
|
Fire alarm contractor did not request an inspection, project associated FIR permits need to be finaled before life fire safety can be performed.
To coincide with Alarm test scheduled by Johnson Controls/TYCO. Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
BLD-Ceiling Grid Inspection | 5/12/2019 | 5/13/2019 | 5/13/2019 | A | PEND |
Brandon Shaw
|
|
|
OK to cover, pending Mech rough-in...
|
BLD-Framing/Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to cover...
|
BLD-Framing/Rough-in | 4/8/2019 | 4/8/2019 | 4/8/2019 | P | NR |
Brandon Shaw
|
|
|
Plumbing/Electrical rough-in in AM Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|