FIRE-Final Inspection | 7/17/2019 | 7/18/2019 | 7/17/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alam inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Ravenswood Solutions TI
|
BLD-Final | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | NR |
Jim Storey
|
|
|
Mark Phone #: ###-####
|
FIRE-Final Inspection | 7/8/2019 | 7/11/2019 | 7/11/2019 | A | CANC |
Jim Page
|
|
|
Fire alarm inspection was cancelled due to wiring issues, point of contact for life fire safety notified me about issue and cancelled this inspection request, life fire safety inspection will be rescheduled for a later date to coincide with fire alarms after wiring issue is corrected.
Ron Phone #: ###-####-please call when on way so he can meet you there
|
BLD-Ceiling Grid Inspection | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Jim Storey
|
|
|
Mark Phone #: ###-#### ceilling ok to cover.
|
BLD-Ceiling Grid Inspection | 6/21/2019 | 6/24/2019 | 6/24/2019 | A | PART |
Jim Storey
|
|
|
Ron Phone #: ###-#### east big rm needs primtor wires/ all other areas ok to coner.
|
BLD-Energy code compliance | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | PASS |
Jim Storey
|
|
|
Mark Phone #: ###-#### 12 inch push at exit door south/east.
|
BLD-Framing/Rough-in | 4/25/2019 | 4/29/2019 | 4/29/2019 | A | PART |
Jim Sly
|
|
|
Mark Phone #: ###-#### Framing is complete and appears OK.....except asked them to add more bracing to top of walls. Mark wants to one side walls where Electrical has approved rough-in. Plumbing seems to be OK with that..........
|
BLD-Framing/Rough-in | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PART |
Jim Storey
|
|
|
Mark Phone #: ###-#### wip
|