BLD-Final | 11/22/2019 | 11/25/2019 | 11/25/2019 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | PART |
Mike Jordan
|
|
|
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman. Ok for temp occ. ok to see clients. Needs to provide ADA compliant counter at main check in desk.
|
BLD-Final | 7/25/2019 | 7/26/2019 | 7/26/2019 | P | PART |
Tell Riley
|
|
|
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman//temp occupancy to move in equipment//no patient exams until final occupancy//
|
FIRE-Final Inspection | 7/25/2019 | 7/26/2019 | 7/26/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
|
BLD-Ceiling Grid Inspection | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PASS |
Mike Jordan
|
|
|
Early afternoon Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
|
BLD-Ceiling Grid Inspection | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | FAIL |
Mike Jordan
|
|
|
provide means of keeping main and cross runners from spreading.
|
BLD-Ceiling Grid Inspection | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | NR |
Mike Jordan
|
|
|
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman. Mech inspection above grid has failed.
|
BLD-Framing/Rough-in | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Interior steel stud framed walls,hardlids and soffits only.
|