BLD-Final | 4/17/2020 | 4/20/2020 | 4/20/2020 | A | PASS |
Tell Riley
|
|
|
Screened- call for access if possible- Steve Phone #: ###-####
|
DOC - Permit Finaled | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Concrete | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | PASS |
Tell Riley
|
|
|
Steve Phone #: ###-####//rebar for CMU wall//ok when top 4 bar installed per drawings//
|
BLD-Footing | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Tell Riley
|
|
|
Steve Phone #: ###-####//rebar and setbacks verified on previous inspection//cold weather techniques discussed and will be used//
|
BLD-Footing | 12/23/2019 | 12/26/2019 | 12/26/2019 | A | NR |
Tell Riley
|
|
|
We are doing a monolithic pour for a small sunroom/greenhouse addition and are ready for our initial inspection. I live in Caldwell so If I have a general idea when you might be able th get there, I can head out in good time. Thanks. Steve Phone #: ###-#### Inspection requested via web by Steve Herring//Steve will call in when day of or before pour--due to cold weather concrete provisions//
|