Permit Information
Permit NumberBLD19-01109
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 5450 W GOWEN RD
Project NameKnife River Office/Shop Bldg
Customer NumberBUILDING 19-00101
ePlanReviewYes
Description
(KNIFE RIVER) FOUNDATION ONLY & UNDERGROUND WORK _ New two story, pre-engineered metal office/warehouse building with an area of 21,690 sq. ft. 1st floor and 9,246 sq. ft. on the 2nd floor. The pre-engineered metal building will be utilized as an office and vehicle repair shop. GRADING & DRAINAGE APPROVED UNDER GRD18-00092. Note: SPECIAL INSPECTIONS REQUIRED SEE FORM 310. **JHB** NOTE: Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor 208-608-7171
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/8/20204/9/20204/9/2020APASS
DetailsJim Storey
final ok
DOC - Permit Finaled4/9/20204/9/20204/9/2020PPASS
DetailsJim Storey
Extend Permit 90/180 days1/10/20201/10/20201/10/2020APASS
DetailsJim Storey
DOC - Permit Finaled1/10/20201/10/20201/10/2020PPASS
DetailsJim Storey
BLD-Conference1/7/20201/7/20201/7/2020PPART
DetailsJim Storey
recieved engineers letter compliant with design and insp. reports archived// need sign offs/ ceilling restraint 2nd foor/ fire top of wall riser rm.
BLD-Final12/17/201912/18/201912/18/2019PNR
DetailsMike Jordan
Looking for TCO Phone #: ###-#### Inspection requested via web by leonard loewen. Needs fire/life/safety final as well as public works and zoning. Also needs to submit final elevation cert. to Jason Taylor for approval. Also noted open foundation and under permit as well. Attached electrical permit still open.
BLD-Framing/Rough-in9/24/20199/25/20199/25/2019APASS
DetailsJim Storey
1st floor cover up and second floor partial, drywall progression. Phone #: ###-#### Inspection requested via web by leonard loewen
BLD-Framing/Rough-in9/16/20199/17/20199/17/2019PPASS
DetailsJim Storey
Inspection of insulation at interior walls on level 1 Phone #: ###-#### Inspection requested via web by leonard loewen
BLD-Framing/Rough-in9/9/20199/9/20199/9/2019PPART
DetailsJim Storey
Light gauge framing Phone #: ###-#### Inspection requested via web by leonard loewen walls interior ok pending planreview// need vappor barrior/ need insp of fire rated const.
BLD-Framing/Rough-in8/27/20198/28/20198/28/2019AFAIL
DetailsJim Storey
Framing at vestibule for exterior stucco Phone #: ###-#### Inspection requested via web by leonard loewen remove plywood exterior not fire treated.
BLD-Foundation5/10/20195/15/20195/15/2019APASS
DetailsJim Storey
Phone #: 2084841715 >> Inspection requested via mobile web by Dustin Campbell s/w walls ok si pending
BLD-Foundation5/2/20195/3/20195/3/2019APASS
DetailsJim Storey
Phone #: 2084841715 >> Inspection requested via mobile web by Dustin Campbell east walls to office break// pending si
BLD-Footing4/23/20194/24/20194/24/2019APART
DetailsJim Storey
Phone #: 2084841715 >> Inspection requested via mobile web by Dustin Campbell pending comp. report/ concreate/rebar.