Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberBLD19-01816
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 6031 E HOOTOWL DR
Project NameHarris North Lot 76 Block 1
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 2705 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 309 sq. ft. of covered patio/porch and a 768 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. SP-01 zoning and setbacks per planning. ***RDP*** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final. SPRINKLERS ARE NOT REQUIRED. LGM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/30/201910/31/201910/31/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled10/31/201910/31/201910/31/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results10/31/201910/31/201910/31/2019PDONE
DetailsBrandon Shaw
ACH50- 2.71
BLD-Other8/19/20198/19/20198/19/2019PPASS
DetailsBrandon Shaw
Soffit Inspection please Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Energy code compliance8/13/20198/14/20198/14/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Framing/Rough-in8/7/20198/12/20198/12/2019APASS
DetailsBrandon Shaw
OK to insulate...
BLD-Wall Bracing7/24/20197/25/20197/25/2019PPASS
DetailsBrandon Shaw
Work in progess...
BLD-Foundation6/27/20196/27/20196/27/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing6/26/20196/26/20196/26/2019PPASS
DetailsBrandon Shaw
Work in progress...