Permit Information
Permit NumberBLD19-02339
StatusIssued
Name ESI
Site Address 1100 W IDAHO ST
Project Name11th & Idaho - Shell & Core
Customer NumberESC19-00779
ePlanReviewYes
Description
(11TH AND IDAHO) (SHELL & CORE) **Project Management- Ron Hill **PLAN MOD #2 (7/22/20) REVISED DETAILS FOR 2HR WALL TERMINATION AT EXTERIOR WEST WALL **PLAN MOD (7/7/20) REVISED 2_HR WALL FROM U411 to W440. **NO OCCUPANCY ALLOWED UNDER THIS PERMIT. TENANT SHALL APPLY FOR CERTIFICATE OF OCCUPANCY FOR EACH TENANT PRIOR TO OCCUPYING ANY FLOOR OR ROOFTOP. ** All tenant improvements are required to provide commissioning upon buildout per 2015 IECC. (DRH18-00260) (DRH19-00228) This building is type I-B construction and is fully fire sprinklered because it is a high-rise. Permit is to complete the envelope and tenant improvement phase (Package II) for a 9-story shell & core office building with an occupied roof and mechanical penthouse on the roof level. The building has a total floor area of about 172,610 square feet (approximately 18,990 square feet 1st story, approximately 19,500 square feet second story, and 19,160 square feet 3rd through 9th story). The building has an occupied roof that is not included in the building area. The concrete and structural steel phase was done under permit BLD19-02122 (Package I). Special Inspection is required for concrete, steel (including welding and bolting), fire-resistance coatings, fire stopping, anchors post-installed in hardened concrete, and smoke control system and was provided under Package I. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. A separate permit is required for the fire sprinkler system and shall comply with NFPA 13. The fire alarm system requires a separate permit and is required to comply with NFPA 72, including the smoke detection system, as regulated by the Fire Department. Prior to the issuance of a Certificate of Completion, a commissioning report for the shell and core shall be submitted to and accepted by the code official. See form #308 for system commissioning responsibilities checklist. **JHB**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall cover8/11/20208/12/20208/12/2020APASS
DetailsJim Storey
Please come reinspect 4th floor bathroom for lid cover. 5th and 6th floor for lid cover in bathrooms. Phone #: ###-#### Inspection requested via web by Andy Pense east and main shaft assemblies and penatrations ok// 4 and 5 th ceillings ok shaft protection ok. rfi for coloum protction empeded by horrazontal tube steel must meet 2 hr struc. prorection.
BLD-Wall cover8/10/20208/10/20208/10/2020PPART
DetailsDave Hannah
please come inspect the 3rd and 4th floor bathrooms for lid cover. Phone #: ###-#### Inspection requested via web by Andy Pense ok to cover lids
BLD-Wall cover8/4/20208/4/20208/4/2020PNR
DetailsDave Hannah
Please come inspect mechanical shaft on the East. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover8/3/20208/3/20208/3/2020PPART
DetailsDave Hannah
Please come verify work complete to cover stair 2 first floor 2 hour. First floor loggia for cover in the lobby as well.
Thank you. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover7/29/20207/29/20207/29/2020APASS
DetailsDave Hannah
Please come inspect the ceiling of the North notch. Please come inspect the 3rd and 4th floors for progress and ceiling cover. Progress on the West wall first floor. Progress on stair 2, 2 hour assembly. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Other7/22/20207/22/20207/22/2020PPASS
DetailsJim Storey
*Screened* Interior wall cover, Andy Phone #: ###-#### restarms floor penatrations and walls 5 and 6 ok to cover// reviewed stair 2# penatrations ok wip
BLD-Wall cover7/20/20207/21/20207/21/2020APASS
DetailsMike Jordan
Andy *screened* Phone #: ###-####. Elevator shaft walls for cars 3 and 4 on 10th. floor. Fire proofing patch back on west coloumn north notch. Stair 2 shaft walls floor 6 to 10. main mech shaft floor 3.
BLD-Wall cover7/14/20207/15/20207/17/2020APART
DetailsDave Hannah
Please come inspect the following; Stair 1 and stair 2 for cover, 2 Hr. electrical box in the communication room south shaft wall. North notch East column all the way up to level 10. Fire caulk in the bathrooms 2-3 at the floors, main shaft for cover.
Thanks, Please call if you have any questions. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover6/30/20206/30/20206/30/2020ADONE
DetailsDave Hannah
Please come and inspect the South notch bay East column.
Thanks. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in6/30/20206/30/20206/30/2020PPART
DetailsDave Hannah
column east end of south notch ok to cover
BLD-Wall cover6/26/20206/26/20206/26/2020PPART
DetailsJim Storey
Please come inspect the South notch East side for cover. Contact Andy Pense ###-#### thanks Phone #: ###-#### Inspection requested via web by Andy Pense web patch ok idaho st flange stil nees coverage of fireproofing.
BLD-Wall cover6/24/20206/24/20206/24/2020APART
DetailsDave Hannah
Please come inspect the first floor walls for cover. Inspect the 10th floor shaft liner. Phone #: ###-#### Inspection requested via web by Andy Pense first floor north corrador ok
BLD-Wall cover6/15/20206/16/20206/16/2020APART
DetailsDave Hannah
Please come inspect the South Notch East wall 2-9. Call Andy with any questions. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover6/11/20206/12/20206/12/2020APEND
DetailsDave Hannah
Come inspect the south west notch framing for cover. Thanks. Call Andy Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover6/4/20206/5/20206/5/2020APASS
DetailsDave Hannah
Please come inspect the insulation in the electrical room level 1. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in6/3/20206/3/20206/4/2020PPASS
DetailsDave Hannah
Penthouse framing inspection to cover. Please get with Mike Koci Or Andy Pense. Thanks Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in5/19/20205/20/20205/20/2020APASS
DetailsDave Hannah
Please come inspect the shaft wall in the elevator pit 3,4. Also South exterior framing for cover. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover5/18/20205/18/20205/18/2020PPASS
DetailsJim Storey
west cuttin wall minrial wool ok to cover.
BLD-Framing/Rough-in3/19/20203/19/20203/19/2020PPART
DetailsDave Hannah
Inspect NE section of exterior framing on 3,4 ; 5th flrs. Please call when onsite. Thanks! Phone #: ###-#### Inspection requested via web by Mike Koci section on north side ok
FIRE-Conference2/20/20202/20/20202/20/2020ADONE
DetailsJim Page
Temporary standpipe has been placed and is in service.
FIRE-Conference2/13/20202/13/20202/13/2020ADONE
DetailsJim Page
Discussed temporary standpipe approximately 2 weeks ago with site foreman with ESI, temp standpipe has net been installed as of this entry, per section 3313.1 of the 2015 IFC states that a temporary standpipe is required when construction reaches 40 feet, project is past the 40 foot height measurement. ESI superintendent has been notified that the temporary standpipe needs to be installed and operational by 21FEB2020 or a stop work will be placed on project until temporary standpipe is installed. This has been discussed with and supported by Joe Bruce, Fire section supervisor as well as Romeo Gervais, Boise City Fire Marshall.
BLD-Wall cover8/13/20208/14/2020 A 
DetailsDave Hannah
Please come inspect the 6th floor for lid for cover. Inspect framing on stair 1 and stair 2. Inspect mechanical shaft liner for cover levels 7-8-9. Inspect the lobby soft for cover, Electrical is in on the East side of the curtain wall lobby. Phone #: ###-#### >> Inspection requested via web by Andy Pense