BLD-Wall cover | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PASS |
Jim Storey
|
|
|
Please come reinspect 4th floor bathroom for lid cover. 5th and 6th floor for lid cover in bathrooms. Phone #: ###-#### Inspection requested via web by Andy Pense east and main shaft assemblies and penatrations ok// 4 and 5 th ceillings ok shaft protection ok. rfi for coloum protction empeded by horrazontal tube steel must meet 2 hr struc. prorection.
|
BLD-Wall cover | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PART |
Dave Hannah
|
|
|
please come inspect the 3rd and 4th floor bathrooms for lid cover. Phone #: ###-#### Inspection requested via web by Andy Pense ok to cover lids
|
BLD-Wall cover | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | NR |
Dave Hannah
|
|
|
Please come inspect mechanical shaft on the East. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Wall cover | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PART |
Dave Hannah
|
|
|
Please come verify work complete to cover stair 2 first floor 2 hour. First floor loggia for cover in the lobby as well. Thank you. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Wall cover | 7/29/2020 | 7/29/2020 | 7/29/2020 | A | PASS |
Dave Hannah
|
|
|
Please come inspect the ceiling of the North notch. Please come inspect the 3rd and 4th floors for progress and ceiling cover. Progress on the West wall first floor. Progress on stair 2, 2 hour assembly. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Other | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PASS |
Jim Storey
|
|
|
*Screened* Interior wall cover, Andy Phone #: ###-#### restarms floor penatrations and walls 5 and 6 ok to cover// reviewed stair 2# penatrations ok wip
|
BLD-Wall cover | 7/20/2020 | 7/21/2020 | 7/21/2020 | A | PASS |
Mike Jordan
|
|
|
Andy *screened* Phone #: ###-####. Elevator shaft walls for cars 3 and 4 on 10th. floor. Fire proofing patch back on west coloumn north notch. Stair 2 shaft walls floor 6 to 10. main mech shaft floor 3.
|
BLD-Wall cover | 7/14/2020 | 7/15/2020 | 7/17/2020 | A | PART |
Dave Hannah
|
|
|
Please come inspect the following; Stair 1 and stair 2 for cover, 2 Hr. electrical box in the communication room south shaft wall. North notch East column all the way up to level 10. Fire caulk in the bathrooms 2-3 at the floors, main shaft for cover. Thanks, Please call if you have any questions. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Wall cover | 6/30/2020 | 6/30/2020 | 6/30/2020 | A | DONE |
Dave Hannah
|
|
|
Please come and inspect the South notch bay East column. Thanks. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Framing/Rough-in | 6/30/2020 | 6/30/2020 | 6/30/2020 | P | PART |
Dave Hannah
|
|
|
column east end of south notch ok to cover
|
BLD-Wall cover | 6/26/2020 | 6/26/2020 | 6/26/2020 | P | PART |
Jim Storey
|
|
|
Please come inspect the South notch East side for cover. Contact Andy Pense ###-#### thanks Phone #: ###-#### Inspection requested via web by Andy Pense web patch ok idaho st flange stil nees coverage of fireproofing.
|
BLD-Wall cover | 6/24/2020 | 6/24/2020 | 6/24/2020 | A | PART |
Dave Hannah
|
|
|
Please come inspect the first floor walls for cover. Inspect the 10th floor shaft liner. Phone #: ###-#### Inspection requested via web by Andy Pense first floor north corrador ok
|
BLD-Wall cover | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PART |
Dave Hannah
|
|
|
Please come inspect the South Notch East wall 2-9. Call Andy with any questions. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Wall cover | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PEND |
Dave Hannah
|
|
|
Come inspect the south west notch framing for cover. Thanks. Call Andy Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Wall cover | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | PASS |
Dave Hannah
|
|
|
Please come inspect the insulation in the electrical room level 1. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Framing/Rough-in | 6/3/2020 | 6/3/2020 | 6/4/2020 | P | PASS |
Dave Hannah
|
|
|
Penthouse framing inspection to cover. Please get with Mike Koci Or Andy Pense. Thanks Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Framing/Rough-in | 5/19/2020 | 5/20/2020 | 5/20/2020 | A | PASS |
Dave Hannah
|
|
|
Please come inspect the shaft wall in the elevator pit 3,4. Also South exterior framing for cover. Phone #: ###-#### Inspection requested via web by Andy Pense
|
BLD-Wall cover | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PASS |
Jim Storey
|
|
|
west cuttin wall minrial wool ok to cover.
|
BLD-Framing/Rough-in | 3/19/2020 | 3/19/2020 | 3/19/2020 | P | PART |
Dave Hannah
|
|
|
Inspect NE section of exterior framing on 3,4 ; 5th flrs. Please call when onsite. Thanks! Phone #: ###-#### Inspection requested via web by Mike Koci section on north side ok
|
FIRE-Conference | 2/20/2020 | 2/20/2020 | 2/20/2020 | A | DONE |
Jim Page
|
|
|
Temporary standpipe has been placed and is in service.
|
FIRE-Conference | 2/13/2020 | 2/13/2020 | 2/13/2020 | A | DONE |
Jim Page
|
|
|
Discussed temporary standpipe approximately 2 weeks ago with site foreman with ESI, temp standpipe has net been installed as of this entry, per section 3313.1 of the 2015 IFC states that a temporary standpipe is required when construction reaches 40 feet, project is past the 40 foot height measurement. ESI superintendent has been notified that the temporary standpipe needs to be installed and operational by 21FEB2020 or a stop work will be placed on project until temporary standpipe is installed. This has been discussed with and supported by Joe Bruce, Fire section supervisor as well as Romeo Gervais, Boise City Fire Marshall.
|
BLD-Wall cover | 8/13/2020 | 8/14/2020 | | A | |
Dave Hannah
|
|
|
Please come inspect the 6th floor for lid for cover. Inspect framing on stair 1 and stair 2. Inspect mechanical shaft liner for cover levels 7-8-9. Inspect the lobby soft for cover, Electrical is in on the East side of the curtain wall lobby. Phone #: ###-#### >> Inspection requested via web by Andy Pense
|