BLD-Final | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Tony Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | PASS |
Tell Riley
|
|
|
firecaulk complete//grid ok//
|
BLD-Ceiling Grid Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | NR |
Tell Riley
|
|
|
Tony Phone #: ###-####//need to firecaulk all penetrations through 2 hour wall//
|
BLD-Ceiling Grid Inspection | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | NR |
Mike Jordan
|
|
|
Tony Phone #: ###-####. A mech. permit is required for the new and altered duct work that has been installed.
|
BLD-Framing/Rough-in | 9/3/2019 | 9/3/2019 | 9/3/2019 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Walls have been repaired. Inteior steel stud framed walls ok. No grid at this time.
|
BLD-Framing/Rough-in | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | FAIL |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Brace testing room walss as required. Firecaulk all penetrations in perimeter fire walls. Correction notice posted.
|