BLD-Final | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PASS |
Dave Hannah
|
|
|
Gaciela Phone #: ###-####
|
DOC - Permit Finaled | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 3/30/2020 | 3/31/2020 | 3/31/2020 | A | NR |
Tell Riley
|
|
|
Graciela Phone #: ###-####//need to add smoke detectors outside bedrooms on on each end of home//need steps out the bedroom door//
|
BLD-Energy code compliance | 3/2/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Dave Hannah
|
|
|
Graciela Phone #: ###-####
|
BLD-Energy code compliance | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | NR |
Dave Hannah
|
|
|
gRACIELA Phone #: ###-#### needs to add one more layer of r19 in attic
|
BLD-Framing/Rough-in | 2/28/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Jim Storey
|
|
|
Graciela Phone #: ###-####
|
BLD-Framing/Rough-in | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | NR |
Tell Riley
|
|
|
Graciela Phone #: ###-####//need to add studs at plate breaks near center door//need mechanical inspection//need electrical inspection//do not insulate until framing is approved//
|
BLD-Conference | 1/27/2020 | 2/3/2020 | 2/3/2020 | P | DONE |
Tell Riley
|
|
|
Graciela Phone #: ###-####//shear ok//truss issues were discussed//
|
BLD-Framing/Rough-in | 1/22/2020 | 1/23/2020 | 1/23/2020 | P | FAIL |
Tell Riley
|
|
|
Graciela Phone #: ###-####//needed shear--failed--discussed onsite//CN issued//will need plan mod for moved wall or meet plans//roof framing does not meet plans either//
|
BLD-Foundation | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Tell Riley
|
|
|
Graciela Phone #: ###-####//ok--left cold weather guide--blankets onsite//
|
BLD-Foundation | 11/21/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Tell Riley
|
|
|
Victor Phone #: ###-####//per plans//footings only//
|