BLD-Final | 5/14/2020 | 5/15/2020 | 5/15/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll. Ok for perm occ.
|
BLD-Final | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PART |
Mike Jordan
|
|
|
Call for access Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll. Ok for temp. occ. Noted vertical grab bars not within the 39 to 41 inch.
|
FIRE-Final Inspection | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll
|
FIRE-Final Inspection | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll
|
FIRE-Final Inspection | 4/28/2020 | 4/29/2020 | 4/29/2020 | P | FAIL |
Troy Cobbley
|
|
|
Still need the emergency lights repaired for a life safety final.
Screened-ARMANDO Phone #: ###-####
|
FIRE-Final Inspection | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | FAIL |
Troy Cobbley
|
|
|
Provide small documents, provide address as discussed, repair emergency lights as marked on the city approved plans.
*screened* Armando Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Mike Jordan
|
|
|
*screened* Amando Phone #: ###-####
|
BLD-Energy code compliance | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Mike Jordan
|
|
|
Armando Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Mike Jordan
|
|
|
armando Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD-Other | 2/6/2020 | 2/6/2020 | 2/6/2020 | P | DEFR |
Mike Jordan
|
|
|
roof before cover // Armando Phone #: ###-####. Ok to cover pending special inspection.
|
BLD-Framing/Rough-in | 1/22/2020 | 1/23/2020 | 1/23/2020 | A | PASS |
Mike Jordan
|
|
|
Armando Phone #: ###-####. Exterior sheathing ok. Verified sheeting is fire treated.
|
BLD-Framing/Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Mike Jordan
|
|
|
armando Phone #: ###-####. Exterior steel stud walls and roof for compressor room ok to shaeet.
|
BLD-Other | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PART |
Mike Jordan
|
|
|
Armando- massory inspection Phone #: ###-####. Work in progress on south east corner of masonry wall at 8ft. to 12ft. elevation. Ok for grout pending special inspection.
|
BLD-Concrete | 12/13/2019 | 12/16/2019 | 12/16/2019 | A | DEFR |
Mike Jordan
|
|
|
Aramado- pouring concrete please as early as possible Phone #: ###-####. Work in progress. Ok to grout pending special inspection.
|
BLD-Foundation | 11/27/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Mike Jordan
|
|
|
rebar // Armando Phone #: ###-####. Interior slab on grade.
|
BLD-Footing | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PART |
Mike Jordan
|
|
|
Armando Phone #: ###-####. West stemwall, work in progress. Ok to place concrete pending special inspection.
|
BLD-Foundation | 11/14/2019 | 11/15/2019 | 11/18/2019 | A | PASS |
Dave Hannah
|
|
|
rebar // armondo Phone #: ###-####
|
BLD-Foundation | 11/6/2019 | 11/8/2019 | 11/8/2019 | P | PEND |
Dave Hannah
|
|
|
rebar // Armando Phone #: ###-#### this is a ftg inspection looks good but not done spec inspection will sign off monday befor placement
|