BLD-Final | 12/12/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 12/12/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection for scope of work complete, fire alarm inspection for scope of work is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for scope of work is complete, signatures provided on permit signature card.
|
BLD-Final | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | CANC |
Jim Storey
|
|
|
this is for CO . fire life will be inspecting Thursday Please call with any questions. Thank you Phone #: ###-#### Inspection requested via web by Mark Coiner
|
FIRE-Alarm Testing | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | PART |
Jim Page
|
|
|
All emergency lighting tested during this inspection, all fire exitnguishers are in place. Life fire safety cannot be signed off until FIR permit for fire alarms is finaled.
smoke test on 4 exterior RTU''s, ,life safety , EM lite test for full CO Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Final | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | DEFR |
Jim Storey
|
|
|
this is for CO . fire life will be inspecting Thursday Please call with any questions. Thank you Phone #: ###-#### Inspection requested via web by Mark Coiner voice mail full need fire and plm insp to be complet pend ing. rolled insp to pm thursday.
|
FIRE-Final Inspection | 10/31/2019 | 10/31/2019 | 10/31/2019 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection for office area is complete (Office scope FIR permit is finaled), fire alarm inspection for TCO is complete (have items that need to be inspected after permenant power is established), fire extinguishers are placed with current inspection tags. Per conversation with Ron Johnson, TCO for life fire safety is autorized for 90 days, signatures provided on signature card for temporary occupancy.
fire sprinkler spray issues were resolved, 2 heads changed out , and EM''s are installed as per design. If possible a 10-12 noon inspection is requested. Thank you Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Final | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PART |
Jim Storey
|
|
|
TCO building inspection fire inspection requested today also. Phone #: ###-#### Inspection requested via web by Mark Coiner tco ok upon fire sign off.
|
FIRE-Final Inspection | 10/28/2019 | 10/29/2019 | 10/29/2019 | P | FAIL |
Jim Page
|
|
|
Emergency lighting does not match the city approved drawings. FIR permit for fire sprinkler in office remodel area needs to be finaled before TCO.
Final inspection for TCO, fire life inspection Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Final | 10/22/2019 | 10/25/2019 | 10/25/2019 | A | NR |
Jim Storey
|
|
|
For TCO Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Ceiling Grid Inspection | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Coiner// mains need wire support 8 inches from ends// pending trades.
|
BLD-Framing/Rough-in | 10/1/2019 | 10/3/2019 | 10/3/2019 | A | PASS |
Jim Storey
|
|
|
early am requested...thank you Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Energy code compliance | 10/3/2019 | 10/3/2019 | 10/3/2019 | A | PASS |
Jim Storey
|
|
|
early am requested...thank you Phone #: ###-#### Inspection requested via web by Mark Coiner roof and walls insulation complet and aproved.
|
BLD-Framing/Rough-in | 9/30/2019 | 10/2/2019 | 10/1/2019 | A | CANC |
Jim Storey
|
|
|
MEP rough in inspections should be completed by 10-2-2019 Phone #: ###-#### >> Inspection requested via web by Mark Coiner Inspection cancelled from web by: Mark Coiner
|