BLD-Final | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
DOC - Permit Finaled | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Mike Jordan
|
|
|
All issues were resolved.
|
BLD-Blower Door Test Results | 3/3/2020 | 3/3/2020 | 3/3/2020 | A | DONE |
Mike Jordan
|
|
|
5.5
|
BLD-Final | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | NR |
Tell Riley
|
|
|
Jeff Phone #: ###-####//install attic access door//insulate crawl access door//seal penetrations through garage separation wall//provide blower door test//CN posted//
|
BLD-Energy code compliance | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/4/2019 | 12/4/2019 | 12/4/2019 | P | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####//corrections made//engineering provided for trusses installed backwards--gussetts nailing and added webs installed per engineering//ok to insulate//
|
BLD-Framing/Rough-in | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | FAIL |
Tell Riley
|
|
|
jeff Phone #: ###-####//CN posted//need to fix truss clip north wall//add stud to beam pocket per engineering//add strap to portal frame on interior side per detail//provide engineered truss letter or fix for truss bearing points not lining up on wall per truss plans//
|
BLD-Wall Bracing | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | PASS |
Dave Hannah
|
|
|
shear // Jeff Phone #: ###-####
|
BLD-Footing | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Tell Riley
|
|
|
James Phone #: ###-####//ok per plans//
|