Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD19-03238
StatusIssued
Name OPUS DESIGN BUILD LLC
Site Address 412 S 3RD ST
Project Name3rd & Myrtle Shell/Core
Customer NumberBLD19-04432
ePlanReviewYes
Description
***GREEN TAG-PRIORTY REVIEW-PROJET MANAGEMENT-Angie Brosious*** (3RD & MYRTLE) (SHELL/CORE ONLY) (DRH19-00007) (GRD19-00067 Grading/Utilities) (BLD19-02943 Foundation) Permit to construct the shell and core of the Type IA podium and the Type IIIA building above for an 8-story, mixed-use residential housing project. Work to include: construction of Type IA podium including foundation, structural steel, PT concrete slab and exterior walls; construction of Type IIIA structure including wood framed exterior walls, floors, roof, and interior bearing walls; construction of interior core including stair, elevator, and mechanical shafts. Special inspections required per the attached Form 310. Special Inspection survey required to verify low point of grade at beginning of construction, building height of top of podium, 5th flr, and 8th flr at framing stage, at 8th flr final construction. Deferred submittals as listed on G0.01. Approval contingent upon adhering to the approved plans on file and attached engineering. This building will be sprinklered with a fully compliant NFPA 13 and NFPA fire alarm system for occupancy, allowable area increase, and height increase. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Conference8/6/20208/6/20208/6/2020ADONE
DetailsJim Page
Fire conference is complete. As discussed the temporary standpipe for fire protection needs to comply with section 3313 of the 2015 IFC, as of this entry, the standpipe only goes to level 4 of the parking garage. Means of egress needs to comply with section 3311 of the 2015 IFC as well. Standpipe must meet the requirements mentioned by 12AUG2020 or a stop work will be placed on the project until the requirements are met.
BLD-Framing/Rough-in7/29/20207/30/20207/30/2020APART
DetailsDave Hannah
Joe Phone #: ###-#### ok steel studs 1st 2nd and 3rd ok mto prerock and insulate
BLD-Framing/Rough-in6/17/20206/18/20206/18/2020PPART
DetailsDave Hannah
screened // joe Phone #: 208-###-#### second and third floor ext steel stud framing ok to sheet ext