FIRE-Final Inspection | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | CANC |
Jim Page
|
|
|
Life safety signed off on 02JULY2020 for this permit, this request is cancelled.
Rod- */Screened*/ Phone #: ###-####
|
BLD-Final | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PASS |
Jim Storey
|
|
|
Need Life Safety ; Bld Final Phone #: ###-#### Inspection requested via web by Rod Baxter
|
DOC - Permit Finaled | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PART |
Brandon Shaw
|
|
|
Temp C of O is approved...
|
FIRE-Final Inspection | 7/2/2020 | 7/2/2020 | 7/2/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags, knox box is located by fire sprinklerriser, fire pump room. Final life fire safety inspection for core and shell complete, signature provided on permit sign off card.
|
BLD-Other | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | CANC |
Brandon Shaw
|
|
|
TCO/Life Safety Call Rod Baxter when you get onsite Please Phone #: ###-#### Inspection requested via web by Rod Baxter
|
BLD-Framing/Rough-in | 5/18/2020 | 5/19/2020 | 5/19/2020 | A | PASS |
Jim Storey
|
|
|
call Rod Baxter upon arrival to site. Phone #: ###-#### Inspection requested via web by Rod Baxter
|
BLD-Energy code compliance | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | PASS |
Jim Storey
|
|
|
Verify R-Value of 30 at Roof. Rod Baxter Phone #: ###-#### Inspection requested via web by Rod Baxter revised iecc report. ok
|
BLD-Energy code compliance | 3/17/2020 | 3/18/2020 | 3/18/2020 | P | FAIL |
Jim Storey
|
|
|
Inspection at Roofing Insulation Phone #: ###-#### Inspection requested via web by Rod Baxter r 38 min required.
|
BLD-Wall Bracing | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Jim Storey
|
|
|
Joist Welding Inspection , Tilt Panel Welding Inspection Phone #: ###-#### Inspection requested via web by Rod Baxter// pannel base welds and joist welding in progress.
|
BLD-Footing | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Rod Baxter north end rebar ok wip si pending.
|
BLD-Footing | 2/5/2020 | 2/7/2020 | 2/6/2020 | A | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Rod Baxter Inspection cancelled from web by: Rod Baxter
|
BLD-Footing | 2/4/2020 | 2/5/2020 | 2/5/2020 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Rod Baxter Inspection cancelled from web by: Rod Baxter
|
BLD-Foundation | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | CANC |
Jim Storey
|
|
|
Tilt Panel Inspection. Phone #: ###-#### Inspection requested via web by Rod Baxter
|
BLD-Footing | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Jim Storey
|
|
|
Interior Spread Footings Phone #: ###-#### Inspection requested via web by Rod Baxter si on site pending reports rebar pass
|