BLD-Final | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Tell Riley
|
|
|
Call for access Phone #: 2089417066 >> Inspection requested via mobile web by Anthony Day
|
DOC - Permit Finaled | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Blower Door Test Results | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | DONE |
Tell Riley
|
|
|
2.92 ACH 50
|
BLD-Energy code compliance | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Mike Jordan
|
|
|
Anthony Phone #: ###-####
|
BLD-Framing/Rough-in | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Mike Jordan
|
|
|
Anthony Phone #: ###-####
|
BLD-Framing/Rough-in | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | FAIL |
Mike Jordan
|
|
|
Anthony Phone #: ###-####. Complete lateral bracing on T15 trusses. Install the missing MSTA 24 straps at RV bay per the engineering. Provide engineering showing the HDU 4 holdownsx at RV bay are sufficient in leiu of the STDH14. Install the missing STDH10 straps at back patio. Install theSTG224 straps at top plate to beam at back patio. Correction notice posted. Ok to insulate.
|
BLD-Framing/Rough-in | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | NR |
Mike Jordan
|
|
|
Anthony Phone #: ###-####. Mech rough in inspection has failed.
|
BLD-Wall Bracing | 11/15/2019 | 11/15/2019 | 11/15/2019 | P | PART |
Mike Jordan
|
|
|
Anthony Phone #: ###-####. missing holdowns at RV bay and rear columns. Ok to tyvek except for those areas.
|
BLD-Foundation | 10/23/2019 | 10/24/2019 | 10/24/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 10/22/2019 | 10/23/2019 | 10/23/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|