FIRE-Final Inspection | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Jim Page
|
|
|
Permenant doors have been installed, final life fire safety inspection for scope of work is complete.
David Phone #: ###-####
|
BLD-Final | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Dave Hannah
|
|
|
David Phone #: ###-####
|
BLD-Final | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | PART |
Dave Hannah
|
|
|
zach Phone #: ###-#### ok for temp occ will need to finish doors
|
FIRE-Final Inspection | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PART |
Jim Page
|
|
|
Partial final life fire safety inspection complete, fire alarm inspection is complete, fire sprinkler inspection is complete, fire extiguishers are placed with current inspection tags. Premenant doors for elevator lobby are on order, temporary doors have been placed for smoke control. 30 day TCO authorized.
zach Phone #: ###-####
|
FIRE-Final Inspection | 1/14/2020 | 1/15/2020 | 1/15/2020 | A | CANC |
Jim Page
|
|
|
Fire alarm permit is still in issued status, needs finaled before life fire safety can be completed, this request is cancelled.
Zach Phone #: ###-####
|
BLD-Conference | 1/13/2020 | 1/13/2020 | 1/14/2020 | P | DONE |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
FIRE-Conference | 1/10/2020 | 1/13/2020 | 1/13/2020 | A | DONE |
Jim Page
|
|
|
Fire conference complete, discussed temporary install of elevator lobby doors due to finish doors being on order, advised point of contact to discuss with structural, if no issue with structural inspector then doors/frames can be used for temp.
Zach Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by David Sferle
|
BLD-Other | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | PASS |
Dave Hannah
|
|
|
Fire Corridor Inspection. Phone #: ###-#### Inspection requested via web by David Sferle
|
BLD-Other | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | NR |
Dave Hannah
|
|
|
13th floor fire corridor Inspection. Phone #: ###-#### Inspection requested via web by David Sferle
|
BLD-Framing/Rough-in | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PASS |
Dave Hannah
|
|
|
zack Phone #: ###-####
|