BLD-Final | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Tell Riley
|
|
|
BRANDY Phone #: ###-####
|
DOC - Permit Finaled | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Conference | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | DONE |
Tell Riley
|
|
|
Call 15 mins berfore- Travis Phone #: ###-####
|
BLD-Final | 11/27/2019 | 11/27/2019 | 11/27/2019 | P | FAIL |
Tell Riley
|
|
|
Brandy Phone #: ###-####//CN posted//need to add anchors on south end per engineering//
|
BLD-Footing | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Brandon Shaw
|
|
|
Brandy Phone #: ###-####
|
BLD-Conference | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | DONE |
Tell Riley
|
|
|
Call 15 mins before-Travis Phone #: ###-####//travis will try to get engineering changed or will add footings as per plan//
|
BLD-Footing | 10/18/2019 | 10/21/2019 | 10/21/2019 | P | FAIL |
Tell Riley
|
|
|
Brandy Phone #: ###-####//frost depth foundation needs to be on all 4 sides of building as displayed on sheet 3 of 6 on the approved engineered plans//
|
BLD-Footing | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | FAIL |
Tell Riley
|
|
|
Brandy Phone #: ###-####//pans show turned down continuous footings for foundaiton//piers were dug and do not reflect enginneering//
|