BLD-Final | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
FIRE-Final Inspection | 1/30/2020 | 1/30/2020 | 1/30/2020 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, fire alarm inspection is complete, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete, signatures provide on permit sign off card.
Zach Phone #: ###-####
|
BLD-Final | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | PART |
Dave Hannah
|
|
|
Zach Phone #: ###-#### ok for tco after fire oks for tco
|
FIRE-Final Inspection | 11/22/2019 | 11/22/2019 | 11/22/2019 | A | PART |
Jim Page
|
|
|
Partial final inspection for life fire safety complete, per conversation with Ron Johson with Boise Fire, a 45 day TCO is authorized for occupancy, final sign off is contingent upon items noted on the 21NOV2019 inspection being completed, inspected and finaled.
|
FIRE-Final Inspection | 11/21/2019 | 11/21/2019 | 11/21/2019 | P | FAIL |
Jim Page
|
|
|
Provide code compliant door hardware throughout space, current door hardware thoughout space is round type door hardware. Area of work requires fire alarm modifications, a seperate fire alarm permit will be required for area of work.
Zach Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | NR |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|