BLD-Blower Door Test Results | 5/7/2020 | 5/7/2020 | 5/7/2020 | A | DONE |
Tell Riley
|
|
|
5.56 ACH 50
|
BLD-Final | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
Tell Riley
|
|
|
Call for access Jeff Phone #: ###-####
|
DOC - Permit Finaled | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Energy code compliance | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####//ok to insulate//
|
BLD-Wall Bracing | 1/6/2020 | 1/6/2020 | 1/6/2020 | P | PASS |
Tell Riley
|
|
|
JEFF Phone #: ###-####//nailing ok//need to add straps at portal frame inside of header--will check at framing//
|
BLD-Foundation | 1/6/2020 | 1/6/2020 | 1/6/2020 | P | DEFR |
Tell Riley
|
|
|
no foundation inspection was scheduled//foundation was poured without inspection//contractor assumes all liability on foundation//
|
BLD-Footing | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PART |
Tell Riley
|
|
|
James Phone #: ###-####//WIP//setbacks ok//will heat bar prior to pour//blankets onsite--cold weather techniques discusses//
|