BLD-Energy code compliance | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | PASS |
Tony Young
|
|
|
Greg - call ahead Phone #: ###-####
|
BLD-Energy code compliance | 5/28/2020 | 5/29/2020 | 5/29/2020 | A | PART |
Tony Young
|
|
|
Greg Phone #: ###-####// seal pack ok
|
BLD-Framing/Rough-in | 5/28/2020 | 5/29/2020 | 5/29/2020 | A | PART |
Tony Young
|
|
|
Greg Phone #: ###-####,, needs truss bracing/ nailing,, ok to insulate,, noted soffits ok also
|
BLD-Wall Bracing | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PART |
Tony Young
|
|
|
Scott - Screened for COVID 19 Phone #: ###-####// exterior ok,, will have interior later
|
BLD-Wall Bracing | 4/10/2020 | 4/13/2020 | 4/13/2020 | A | NR |
Tony Young
|
|
|
Scott - Screened for COVID 19 Phone #: ###-####// need to re-do some areas
|
BLD-Wall Bracing | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | NR |
Tony Young
|
|
|
Greg- screened for COVID 19 symptoms Phone #: ###-####// no one around,, no plans// re-call inspection
|
BLD-Foundation | 3/3/2020 | 3/4/2020 | 3/4/2020 | A | PART |
Tony Young
|
|
|
Pat Phone #: ###-####// late AM,, work in progress,, ok to pour when ready
|
BLD-Foundation | 3/2/2020 | 3/3/2020 | 3/3/2020 | P | NR |
Tony Young
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, footings are work in progress,, ok
|
BLD-Footing | 2/26/2020 | 2/27/2020 | 2/28/2020 | P | CANC |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|