BLD-Final | 7/2/2020 | 7/2/2020 | 7/2/2020 | P | PASS |
Brandon Shaw
|
|
|
After 3 pm please Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 7/2/2020 | 7/2/2020 | 7/2/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/2/2020 | 7/2/2020 | 7/2/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 2.93
|
BLD-Final | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | CANC |
Brandon Shaw
|
|
|
After 3 pm please Phone #: ###-#### >> Inspection requested via web by Daniel Appel Inspection cancelled from web by: Daniel Appel
|
BLD-Wall cover | 4/21/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Brandon Shaw
|
|
|
Insulation...
|
BLD-Framing/Rough-in | 4/21/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | FAIL |
Brandon Shaw
|
|
|
Address to be readily visible from the street... Bedroom 3, first fl, egress window exceeds max height of 44", as is, 50"... Provide straps at break in doulbe top plates- see red marks- bdrm 3 header & top of stairs...
OK to insulate...
|
BLD-Wall Bracing | 3/31/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Wall Bracing | 3/25/2020 | 3/27/2020 | 3/27/2020 | P | FAIL |
Tell Riley
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel//need to add hot dip galvanized nails at PT//nails shear panels marked in red//finish shear panels//add blocks where noted//told him to call back in//
|
BLD-Foundation | 3/3/2020 | 3/4/2020 | 3/4/2020 | A | PASS |
Brandon Shaw
|
|
|
Chris Phone #: ###-####
|
BLD-Foundation | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | NR |
Brandon Shaw
|
|
|
CHRIS- foundation wall Phone #: ###-####
|
BLD-Footing | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 2/26/2020 | 2/27/2020 | 2/27/2020 | P | CANC |
Brandon Shaw
|
|
|
Chris Phone #: ###-####
|