BLD-Energy code compliance | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PART |
Brandon Shaw
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PART |
Brandon Shaw
|
|
|
Pending Engineering approval for header and opening in garage, interior shear wall...
|
BLD-Framing/Rough-in | 4/30/2020 | 5/1/2020 | 5/1/2020 | A | FAIL |
Brandon Shaw
|
|
|
Addres to be readily visable... Provide truss Engineering... Provide revised Engineering for compromised shear wall, with beam calcs, see plans pg. 4... Per plans- beam and columns to be as per schedule, see plans... OK to insulate...
|
BLD-Wall Bracing | 3/24/2020 | 3/26/2020 | 3/26/2020 | A | PART |
Tell Riley
|
|
|
shear // Mark Phone #: ###-####//nailing ok--need to add hot dip galvanized at PT plate//blocking ok//need to add hold downs/bolts--provide engineers alternative for the bolted holddowns in place of speced hold downs//ok to wrap if hot dip nails are visible for re-inspection//
|
BLD-Foundation | 2/13/2020 | 2/13/2020 | 2/13/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | NR |
Brandon Shaw
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | NR |
Brandon Shaw
|
|
|
Need Geo approval for soil subgrade at garage wall, west side...
|