BLD-Foundation | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PEND |
Tell Riley
|
|
|
Sergio - Foundation walls are outside of the modified footing area. */Screened*/ Phone #: ###-####//special inspection report, for post installed anchors, verified by pull test, was in compliance with design engineer--also engineer called me and verified// //plans show hair pins at corners with hold down anchor bolts--engineer called and wants detail deleted from plans--advised to submit with current plan mod under review for footings// //let GC know about my concerns with elevations, we discussed elevtations, wall height seems extremely high, wall currently 2' 8" above footing, plans show a 2' wall on structurals, will need to meet accessiblity requirements at finals// //if walls are poured prior to acceptance of plan modification for footing changes and wall details, cantractor is pouring at own risk// rebar appears to be installed per the current plans, less the hair pins on corners//
|
BLD-Footing | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PART |
Tell Riley
|
|
|
Serigo *screened* Phone #: ###-####//SOUTH WALL FOOTINGS CLOUDED ON PLANS DATED 6/22/2020 THAT ARE NOT APPROVED PLANS, CONTRACTOR POURING AT OWN RISK UNTIL PLAN MODIFICATION IS SUBMITTED AND APPROVED//REBAR IN THIS LOCATION APPEARS TO BE INSTALLED PER THESE PLANS//areas outside modified footings are ok per the APPROVED plans//advised contractor PLAN MODIFICATION MUST BE APPROVED PRIOR TO GOING VERTICAL WITH FRAMING//maintain all clearances on rebar//
|
BLD-Footing | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | NR |
Tell Riley
|
|
|
Call ahead Sergio - Phone #: ###-####//need to submit to plan review for modifications to structural plans for footing sizes, depths and rebar//also appears to be changes with the roof trusses per the new structural drawings onsite//rebar clearances need to be adjusted/cut away from forms and elevated 3" above grade//
|
BLD-Footing | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | FAIL |
Tell Riley
|
|
|
Sergio Phone #: ###-####//CN posted//need small documents//special inspections reqiured//rebar does not meet installation requirements on plans//site does not meet minimum ESC requirements//need all property lines identified and/or marked//
|