BLD-Energy code compliance | 4/2/2020 | 4/3/2020 | 4/3/2020 | A | PASS |
Mike Jordan
|
|
|
Trevor Phone #: ###-####. Letter from engineer provided accepting the garage portal frame construction.
|
BLD-Framing/Rough-in | 3/30/2020 | 3/31/2020 | 3/31/2020 | A | PEND |
Brandon Shaw
|
|
|
See wall brace entry...
|
BLD-Framing/Rough-in | 3/27/2020 | 3/30/2020 | 3/30/2020 | A | FAIL |
Brandon Shaw
|
|
|
No city approved plans on site... No air/ foam seal at time of inspection...
|
BLD-Framing/Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | DEFR |
Jim Storey
|
|
|
Trevor Phone #: ###-#### out of time
|
BLD-Framing/Rough-in | 3/12/2020 | 3/12/2020 | 3/12/2020 | P | PART |
Brandon Shaw
|
|
|
Shear walls... As builts do not match Engineering pg, Simpson Strong Walls 12x9 to be approved by Engineer of record...
|
BLD-Foundation | 1/14/2020 | 1/15/2020 | 1/15/2020 | P | PART |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
BLD-Footing | 1/10/2020 | 1/13/2020 | 1/13/2020 | P | PASS |
Jim Storey
|
|
|
dane Phone #: ###-####
|
BLD-Foundation | 1/9/2020 | 1/10/2020 | 1/10/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|