BLD-Final | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.41
|
BLD-Final | 6/10/2020 | 6/10/2020 | 6/10/2020 | A | NR |
Brandon Shaw
|
|
|
Need PW hillside approval...
|
BLD-Blower Door Test Results | 6/10/2020 | 6/10/2020 | 6/10/2020 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.41
|
BLD-Framing/Rough-in | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Brandon Shaw
|
|
|
If plans are missing, make sure the siders did not steal them Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 3/4/2020 | 3/4/2020 | 3/4/2020 | P | FAIL |
Brandon Shaw
|
|
|
No city approved plans on site...
|
BLD-Other | 3/2/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 2/13/2020 | 2/13/2020 | 2/13/2020 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|