Permit Information
Permit NumberBLD20-00219
StatusIssued
Name 208 NORTHWEST CONSTRUCTION LLC
Site Address 8055 W GODDARD RD
Project NameCapital HS Concession-Pressbox
Customer Number 
ePlanReviewYes
Description
(CAPITAL HIGH SCHOOL CONCESSION/PRESSBOX) **EXPEDITED REVIEW** Permit for demolition of existing overhang structure at back of bleachers and construction of new 2-story, 234 square foot wood-framed outbuilding for Capital High School's softball field to contain concessions on the first floor and a press box above on the second floor. Scope of work includes related site work as shown on approved plans including accessible route. Special inspection required per attached Form 310. All work per approved plans and Engineering. This building is NOT fire sprinklered. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/31/20207/31/20207/31/2020PNR
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Ted Perry//see correction notice//need public works sign off as well//
FIRE-Final Inspection7/29/20207/29/20207/30/2020PPASS
DetailsTroy Cobbley
life safety passed. Phone #: ###-#### Inspection requested via web by Ted Perry
BLD-Final7/28/20207/28/20207/28/2020PNR
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Ted Perry//need zoning and fire life safety finals prior to building final//
BLD-Energy code compliance6/18/20206/18/20206/18/2020APART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Ted Perry//insulation--architect changed and Ted will send email//1" closed cell foam-R7 and R15 batts in wall//room 2" closed cell foam R14 and R15 batts//ok pending architects letter//stairs still under constrution and will be as built by engineer--per Ted//trades ok--no mechanical was installed--let Ted know to contact plan review to remove from requirements//
BLD-Framing/Rough-in6/12/20206/12/20206/12/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Ted Perry//1st floor ok, 2nd floor needs a35s installed-Ted will take photos//ted said nailing on exterior was completed prior to siding going on//ok to insulate//stairs still a WIP, need details from engineer//
BLD-Framing/Rough-in6/2/20206/3/20206/3/2020AFAIL
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Ted Perry//cn left onsite with contracor//see details for framing//add nails and a35s for shear per plan//need alt design for stairs and landing as they do not reflect plans//
BLD-Framing/Rough-in6/2/20206/2/20206/2/2020PCANC
DetailsTell Riley
BLD-Framing/Rough-in6/1/20206/2/20206/2/2020ACANC
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Ted Perry
BLD-Footing4/27/20204/27/20204/27/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Ted Perry//need to have electrical sign off on ground//footings WIP, main area bar ok pending specials//piers are still being installed-WIP//pour is pending specials approval//