BLD-Energy code compliance | 7/24/2020 | 7/27/2020 | 7/27/2020 | A | PASS |
Tell Riley
|
|
|
screened // Vinnie Phone #: ###-####
|
BLD-Framing/Rough-in | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Tell Riley
|
|
|
Vinny- */Screened*/ Phone #: ###-####//ok to insulate//
|
BLD-Framing/Rough-in | 7/21/2020 | 7/21/2020 | 7/21/2020 | P | FAIL |
Tell Riley
|
|
|
SCREENED // Vinny Phone #: ###-####//CN posted//need air seal completed and other framing corrections//
|
BLD-Wall Bracing | 6/30/2020 | 7/1/2020 | 7/1/2020 | A | PASS |
Tell Riley
|
|
|
Vinny *screened* Phone #: ###-####//ok when HD galvanized nails added to Pt plate//
|
BLD-Foundation | 6/16/2020 | 6/17/2020 | 6/17/2020 | P | CANC |
Tell Riley
|
|
|
Dane *screened* Phone #: ###-####
|
BLD-Foundation | 6/15/2020 | 6/16/2020 | 6/16/2020 | P | PART |
Tell Riley
|
|
|
Screened-foundation wall Phone #: ###-####//ok//still need to remove rebar from plans//setbacks still appear to be ok//WIP//
|
BLD-Footing | 6/10/2020 | 6/15/2020 | 6/15/2020 | P | PART |
Tell Riley
|
|
|
screened // Dane Phone #: ###-####//setbacks measured, ok per plans, will need to re-verify at wall inspection//rebar in pads and at garage wall//contractor needs to have rebar on all areas removed from plans as the plans show rebar and he requested not to install rebar//WIP//mud needs to be removed in wet areas as discussed//
|