Permit Information
Permit NumberBLD20-00230
StatusIssued
Name ANDY THOMPSON CONSTRUCTION INC
Site Address 9405 W USTICK RD
Project NameDuplex addition 9405 & 9403
Customer Number 
ePlanReviewYes
Description
Permit for the addition of a new 1,511sq', two story, 3bd/2.5bth home to an existing home, creating a duplex. Home is 878sq' on the main floor, 633sq' on the 2nd level and has a 440sq; attached garage. All work per plans, notations, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Energy code compliance6/22/20206/22/20206/22/2020PPASS
DetailsTell Riley
pass with Res check provided by designer//add Vb at garage separation wall as discussed//
BLD-Framing/Rough-in6/21/20206/22/20206/22/2020APASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//framing corrections made//
BLD-Energy code compliance6/17/20206/19/20206/19/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//u-values and R values do not meet minimum code//provide res-check to meet code minimums as discussed on frame walk through//repair joist per engineering//add VB to garage separation wall//other framing corrections completed//if walls are covered, at own risk and energy code requirements will need to be met//
BLD-Framing/Rough-in6/17/20206/18/20206/18/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//see CN posted for minor framing corrections//ok to insualate only//
BLD-Framing/Rough-in6/17/20206/18/20206/18/2020ACANC
DetailsTell Riley
Phone #: ###-#### >> Inspection requested via web by Andy Thompson Inspection cancelled from web by: Andy Thompson
BLD-Framing/Rough-in6/17/20206/17/20206/17/2020PNR
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//need mechanical, did walk through for corrections//will need re-insepction//
BLD-Wall cover6/4/20206/4/20206/4/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//wall bracing inspection//nails added in areas while onsite//add blocking on shear panels between trusses and nail//add hold down on corner-see plans//add straps on inside of PFH//exterior ok to wrap//
BLD-Wall Bracing6/3/20206/3/20206/3/2020PNR
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//need approved plans onsite//will re-schedule//
BLD-Concrete5/1/20205/1/20205/1/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//concrete was already poured//could see edges of VB//
BLD-Energy code compliance4/28/20204/28/20204/28/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//foundation insulation for slab on grade--ok per plans//
BLD-Foundation4/24/20204/27/20204/27/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//bar in correct locations//setbacks were measure due to footings being poured prior to inspection, they appear to be ok//wall ok, contractor assumes all liablity on footings as they were poured prior to inspection//
BLD-Footing4/24/20204/27/20204/27/2020ADEFR
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Andy Thompson//footings were poured prior to inspection//Contractor assumes all liability for footings//