BLD-Energy code compliance | 6/22/2020 | 6/22/2020 | 6/22/2020 | P | PASS |
Tell Riley
|
|
|
pass with Res check provided by designer//add Vb at garage separation wall as discussed//
|
BLD-Framing/Rough-in | 6/21/2020 | 6/22/2020 | 6/22/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//framing corrections made//
|
BLD-Energy code compliance | 6/17/2020 | 6/19/2020 | 6/19/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//u-values and R values do not meet minimum code//provide res-check to meet code minimums as discussed on frame walk through//repair joist per engineering//add VB to garage separation wall//other framing corrections completed//if walls are covered, at own risk and energy code requirements will need to be met//
|
BLD-Framing/Rough-in | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//see CN posted for minor framing corrections//ok to insualate only//
|
BLD-Framing/Rough-in | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | CANC |
Tell Riley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Andy Thompson Inspection cancelled from web by: Andy Thompson
|
BLD-Framing/Rough-in | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//need mechanical, did walk through for corrections//will need re-insepction//
|
BLD-Wall cover | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//wall bracing inspection//nails added in areas while onsite//add blocking on shear panels between trusses and nail//add hold down on corner-see plans//add straps on inside of PFH//exterior ok to wrap//
|
BLD-Wall Bracing | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//need approved plans onsite//will re-schedule//
|
BLD-Concrete | 5/1/2020 | 5/1/2020 | 5/1/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//concrete was already poured//could see edges of VB//
|
BLD-Energy code compliance | 4/28/2020 | 4/28/2020 | 4/28/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//foundation insulation for slab on grade--ok per plans//
|
BLD-Foundation | 4/24/2020 | 4/27/2020 | 4/27/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//bar in correct locations//setbacks were measure due to footings being poured prior to inspection, they appear to be ok//wall ok, contractor assumes all liablity on footings as they were poured prior to inspection//
|
BLD-Footing | 4/24/2020 | 4/27/2020 | 4/27/2020 | A | DEFR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson//footings were poured prior to inspection//Contractor assumes all liability for footings//
|