Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD20-00366
StatusIssued
Name BENITON CONSTRUCTION
Site Address 1607 N 15TH ST
Project NameWASHINGTON ELEMENTARY ADDITION
Customer Number 
ePlanReviewYes
Description
(WASHINGTON ELEMENTARY)(Project Mangement-Ron Hill) "PLAN MODIFICATION FOR MINOR ALTERATIONS TO THE DRAINAGE SYSTEM GREASE INTERCEPTOR, SIGNAGE AND ELEVATOR DETAILS"" EXPEDITED REVIEW* Construction of a 14,020 sq. ft. addition to the existing 28,476 sq. ft. Washington Elementary school to include administrative offices, a library, gymnasium, and three classrooms to replace the existing portables.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Foundation8/12/20208/13/20208/13/2020PPEND
DetailsTony Young
Grout/Rebar/Masonry inspection request along B grid line. Grouting 35 to 38 feet at 2pm. Dividing wall in the gym between mechanical room 4'' to 8''. MTI scheduled as well. Phone #: ###-#### Inspection requested via web by Dan Koski
BLD-Foundation8/7/20208/7/20208/10/2020PPEND
DetailsTony Young
24-27 foot masonry/rebar grout inspection request. Placing at 2pm today. MTI is scheduled as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski
BLD-Foundation8/4/20208/4/20208/4/2020PPART
DetailsTony Young
20-24 foot lift of Masonry for the gym addition. Rebar/Masonry inspection request. MTI will be on site as well. Grout is at 2pm. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski// masonary pending special inspection.. ?s on shafts.. need to maintain fire wall ratings
BLD-Foundation8/3/20208/3/20208/3/2020PPEND
DetailsTony Young
Masonry/Rebar inspection request for 16 to 20 foot masonry at the new gym. MTI is scheduled to be on site as well. Call Dan with any issues. Grout is at 2pm. Phone #: ###-#### Inspection requested via web by Dan Koski// pending S.I
BLD-Foundation7/30/20207/30/20207/30/2020PPEND
DetailsDave Hannah
Masonry/Rebar inpsection request for new gym. Remaining 12 to 16 feet of masonry being grouted at 2pm. MTI scheduled to be on site as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski ok grout after spec inspection aproves
BLD-Foundation7/29/20207/29/20207/29/2020PPART
DetailsJim Storey
Masonry/Rebar inspection request for the new gym addition. Grouting at 2pm from 12 to 16 feet. MTI will be on site as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski/// ok pending special inspection report
BLD-Foundation7/27/20207/28/20207/28/2020PPART
DetailsTony Young
Grout/Rebar inspection request for Masonry. New gym addition 8 to 12 foot section scheduled for 1pm. Call Dan with any issues. MTI on site as well. Phone #: ###-#### Inspection requested via web by Dan Koski// ok pending special inspection report
BLD-Foundation7/23/20207/23/20207/23/2020PPEND
DetailsTony Young
Rebar/Masonry Inspection request. Grout is at 2pm. MTI is scheduled as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski/// pending special inspection
BLD-Foundation7/21/20207/22/20207/22/2020PPART
DetailsTony Young
Rebar/Masonry inspection request. I didn''t know if Tony was going to want to look at rebar for the structural block in the gym. Grout is scheduled for 3pm. Please call Dan if there are any issues. MTI is on the books as well. Phone #: ###-#### Inspection requested via web by Dan Koski/// work in progress,, pending special inspection
BLD-Concrete7/17/20207/17/20207/17/2020PPART
DetailsBrandon Shaw
VB and Rebar inspection request for the new addition gym slab. Scheduled to place Monday. Special inspection will perform rebar and concrete as well.
special inspection personal on site,, pending approvals...
BLD-Foundation6/23/20206/24/20206/24/2020APASS
DetailsBrandon Shaw
Stem wall placement for the gym. Grids A-B, 1-7. Rebar inspection...
Pending special inspection...
BLD-Footing6/17/20206/18/20206/18/2020APART
DetailsTony Young
Footing rebar inspection request for the Gymnasium Addition. Grids 1-7 and Grids A-B. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski// special inspection personal on site,, pending approvals
BLD-Conference5/27/20205/28/20205/28/2020PPASS
DetailsTony Young
Job-site overview conference meet and greet. Please contact Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski// scope of work meeting