BLD-Foundation | 8/12/2020 | 8/13/2020 | 8/13/2020 | P | PEND |
Tony Young
|
|
|
Grout/Rebar/Masonry inspection request along B grid line. Grouting 35 to 38 feet at 2pm. Dividing wall in the gym between mechanical room 4'' to 8''. MTI scheduled as well. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Foundation | 8/7/2020 | 8/7/2020 | 8/10/2020 | P | PEND |
Tony Young
|
|
|
24-27 foot masonry/rebar grout inspection request. Placing at 2pm today. MTI is scheduled as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Foundation | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | PART |
Tony Young
|
|
|
20-24 foot lift of Masonry for the gym addition. Rebar/Masonry inspection request. MTI will be on site as well. Grout is at 2pm. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski// masonary pending special inspection.. ?s on shafts.. need to maintain fire wall ratings
|
BLD-Foundation | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PEND |
Tony Young
|
|
|
Masonry/Rebar inspection request for 16 to 20 foot masonry at the new gym. MTI is scheduled to be on site as well. Call Dan with any issues. Grout is at 2pm. Phone #: ###-#### Inspection requested via web by Dan Koski// pending S.I
|
BLD-Foundation | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PEND |
Dave Hannah
|
|
|
Masonry/Rebar inpsection request for new gym. Remaining 12 to 16 feet of masonry being grouted at 2pm. MTI scheduled to be on site as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski ok grout after spec inspection aproves
|
BLD-Foundation | 7/29/2020 | 7/29/2020 | 7/29/2020 | P | PART |
Jim Storey
|
|
|
Masonry/Rebar inspection request for the new gym addition. Grouting at 2pm from 12 to 16 feet. MTI will be on site as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski/// ok pending special inspection report
|
BLD-Foundation | 7/27/2020 | 7/28/2020 | 7/28/2020 | P | PART |
Tony Young
|
|
|
Grout/Rebar inspection request for Masonry. New gym addition 8 to 12 foot section scheduled for 1pm. Call Dan with any issues. MTI on site as well. Phone #: ###-#### Inspection requested via web by Dan Koski// ok pending special inspection report
|
BLD-Foundation | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PEND |
Tony Young
|
|
|
Rebar/Masonry Inspection request. Grout is at 2pm. MTI is scheduled as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski/// pending special inspection
|
BLD-Foundation | 7/21/2020 | 7/22/2020 | 7/22/2020 | P | PART |
Tony Young
|
|
|
Rebar/Masonry inspection request. I didn''t know if Tony was going to want to look at rebar for the structural block in the gym. Grout is scheduled for 3pm. Please call Dan if there are any issues. MTI is on the books as well. Phone #: ###-#### Inspection requested via web by Dan Koski/// work in progress,, pending special inspection
|
BLD-Concrete | 7/17/2020 | 7/17/2020 | 7/17/2020 | P | PART |
Brandon Shaw
|
|
|
VB and Rebar inspection request for the new addition gym slab. Scheduled to place Monday. Special inspection will perform rebar and concrete as well. special inspection personal on site,, pending approvals...
|
BLD-Foundation | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Brandon Shaw
|
|
|
Stem wall placement for the gym. Grids A-B, 1-7. Rebar inspection... Pending special inspection...
|
BLD-Footing | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | PART |
Tony Young
|
|
|
Footing rebar inspection request for the Gymnasium Addition. Grids 1-7 and Grids A-B. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski// special inspection personal on site,, pending approvals
|
BLD-Conference | 5/27/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Tony Young
|
|
|
Job-site overview conference meet and greet. Please contact Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski// scope of work meeting
|