BLD-Framing/Rough-in | 7/22/2020 | 7/23/2020 | 7/23/2020 | A | NR |
Tell Riley
|
|
|
ok with video or photo // Jim Phone #: ###-####//need electrical roughed in and inspected//mechanical needs roughed in and inspected//provide truss detail for connections to girders//
|
BLD-Wall Bracing | 6/16/2020 | 6/16/2020 | 6/16/2020 | P | PASS |
Tell Riley
|
|
|
ok to wrap when nails added as dicussed//
|
BLD-Framing/Rough-in | 6/15/2020 | 6/16/2020 | 6/16/2020 | P | CANC |
Tell Riley
|
|
|
James *screened* Phone #: ###-####
|
BLD-Framing/Rough-in | 6/8/2020 | 6/9/2020 | 6/9/2020 | A | NR |
Tell Riley
|
|
|
James *screened* Phone #: ###-####//inspection used as a conference//
|
BLD-Foundation | 5/4/2020 | 5/5/2020 | 5/5/2020 | A | PASS |
Mike Jordan
|
|
|
Brandon Phone #: ###-####
|
BLD-Footing | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | PASS |
Tell Riley
|
|
|
Brandon Phone #: ###-####//side setbacks maintain existing//40 plus feet in rear//ok per plans//
|