BLD-Foundation | 4/14/2020 | 4/15/2020 | 4/16/2020 | P | PASS |
Dave Hannah
|
|
|
Screened- John Phone #: ###-####
|
BLD-Footing | 4/10/2020 | 4/13/2020 | 4/13/2020 | A | PASS |
Mike Jordan
|
|
|
John - Screened for Covid 19 symptoms Phone #: ###-####. East stemwall only ok.
|
BLD-Footing | 4/6/2020 | 4/6/2020 | 4/6/2020 | P | PART |
Mike Jordan
|
|
|
clear call ahead and will pull plans out of trailer for you to look at // John Phone #: ###-####. Perimeter foorings, interior footings. Work is in progress. Will have special inspection. Noted RFI changes to footings have been submitted per the contractor and architect. Contractor to proceed at their own risk.
|