Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD20-01152
StatusIssued
Name EMPIRE CONSTRUCTION COMPANY LLC
Site Address 7008 W EL CABALLO DR
Project Name7008 El Caballo Home
Customer Number 
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY REQUIREMENT**PLAN MODIFICATION: ADDING STAND-ALONE FIREPLACE IN LIVING ROOM** Permit for the construction of a new 1520 sq. ft., one story Single Family Dwelling Unit with 3 bedrooms, 2bathrooms, approximately 288 sq. ft. of covered patio/porch and a 348 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. D_S
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall cover6/29/20207/2/20207/2/2020PPASS
DetailsTell Riley
corrections completed.insulation completed.contact Alex with any questions. ###-#### Phone #: ###-#### Inspection requested via web by Alex Macdonald//corrections completed//Energy ok//add 2 2x8 headers for opening at hallway--Alex will send photos//
BLD-Framing/Rough-in6/25/20206/26/20206/26/2020APART
DetailsTell Riley
Truss plans onsite. Call Alex at ###-#### with any questions. Phone #: ###-#### Inspection requested via web by Alex Macdonald//CN posted for bearing wall corrections at center truss bearing//need to install FP and have inspected//ok to insulate--DO NOT INSULATE AREA WHER FP IS UNTIL IT HAS BEEN INSPECTED//
BLD-Framing/Rough-in6/17/20206/18/20206/18/2020AFAIL
DetailsTell Riley
Call Alex with any questions. ###-####. Thanks! Phone #: ###-#### Inspection requested via web by Alex Macdonald//need truss plans//air seal needs completed//add stud next to cut stud at ele panel//desinger needs to specify headers over angled windows at front and rear of home//
BLD-Wall Bracing5/18/20205/19/20205/19/2020APASS
DetailsTell Riley
Please call Alex at ###-#### with any questions. Phone #: ###-#### Inspection requested via web by Alex Macdonald//ok check hold downs at PFH on framing//
BLD-Wall Bracing5/15/20205/18/20205/18/2020ANR
DetailsTell Riley
Call Alex at ###-#### with any questions! Phone #: ###-#### Inspection requested via web by Alex Macdonald
BLD-Foundation4/30/20205/1/20205/1/2020APART
DetailsTell Riley
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo //side 5' setback right on foundationn wall//front and rear ok// rebar ok per plans//discussed frost depth and drainage on 5' side, as elevation seems high//
BLD-Footing4/29/20204/30/20204/30/2020APART
DetailsTell Riley
south side, front and rear setbacks per plans//side with canal measured at center of bridge meets 15'4" on plans//rebar per plans//talked with Andy about ESC permit, notified concrete guys of washout containment, stated they would washout offsite//north side will need to comply with 2' frost depth requirements and contain water onsite--will need to be addressed by contractor//
BLD-Footing4/28/20204/29/20204/29/2020PNH
DetailsTell Riley
Phone #: 2086971241 >> Inspection requested via mobile web by Heron aggregate construct//no one oniste//will reschedule//