FIRE-Final Inspection | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Ceiling Grid Inspection | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Doug Storey//grid looks ok//Electrical passed//new RTU in end classroom will need to be inspected when installed//pending fire sprinkler approval//
|
BLD-Conference | 7/16/2020 | 7/17/2020 | 7/17/2020 | A | DONE |
Tell Riley
|
|
|
Please call 30 min. prior to make sure we are onsite. Thank you. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Wall Bracing | 7/10/2020 | 7/10/2020 | 7/10/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Doug Storey//scope of permit needs to be updated to remove the phase of work for the auditorium//inspection is on the five classrooms only//wall brackets installed, located on opposite side of previously installed wall brackets to brace the CMU as directed by the architect//no structural details were provided for these brackets//appear to meet sizes per the plans//special inspections were completed for the anchors//
|