BLD-Final | 6/23/2020 | 6/23/2020 | 6/23/2020 | P | DONE |
Tell Riley
|
|
|
Corrections have been made to drawings on site. Please contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### if you have any questions. Thank you. Inspection requested via web by Rob Maes
|
DOC - Permit Finaled | 6/23/2020 | 6/23/2020 | 6/23/2020 | P | PASS |
Tell Riley
|
|
|
setbacks were discussed with Josh at plan review and appear to still be within minimum required by city code//final complete//
|
BLD-Final | 6/19/2020 | 6/19/2020 | 6/19/2020 | A | FAIL |
Tell Riley
|
|
|
need to provide plan for fire setbacks on solar// plan needs to be approved by plan review//
|
BLD-Final | 6/17/2020 | 6/18/2020 | 6/19/2020 | A | CANC |
Tell Riley
|
|
|
|
BLD-Final | 6/16/2020 | 6/17/2020 | 6/17/2020 | P | NR |
Tell Riley
|
|
|
Please contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior if you have any questions. Thanks in advance, Rob Inspection requested via web by Rob Maes//Electrical did not pass// rescheduled for tomorrow//
|
BLD-Final | 6/15/2020 | 6/16/2020 | 6/16/2020 | P | CANC |
Tell Riley
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior as someone will need to meet inspector on site. Thanks in advance. >> Inspection requested via web by Rob Maes Inspection cancelled from web by: Rob Maes
|