BLD-Foundation | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PART |
Tell Riley
|
|
|
Screened- stem wall inspection- Jeff Phone #: ###-####//rear setbacksare tight at 15'-measured from string line offset 5' from pins//will need to maintain 15' setback during construction//rebar per plans//WIP//
|
BLD-Foundation | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | FAIL |
Tell Riley
|
|
|
screened // Jeff Phone #: ###-####//footings poured without inspection//wall appears to meet plans//rear setbacks appear to only be 14' 8" from property line--asked contractor to run an offset line parallel to property line to get an acurate measurement//will need to meet 15' rear setback//
|
BLD-Footing | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | FAIL |
Brandon Shaw
|
|
|
Permit has not been issued...
|