BLD-Wall cover | 8/12/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Mike Jordan
|
|
|
Call Tim 30 minutes prior for access Phone #: ###-#### Inspection requested via web by Timothy Gammill. Shear blocking installed. insulation not completed. Will need to call in energy code inspection when insulation is installed.
|
BLD-Framing/Rough-in | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PART |
Mike Jordan
|
|
|
Call Tim 30 minutes prior for access Phone #: ###-#### Inspection requested via web by Timothy Gammill. complete airseal, and install shear blocking.
|
BLD-Foundation | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Mike Jordan
|
|
|
virtual inspection // Greg Phone #: ###-####
|
BLD-Foundation | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | CANC |
Mike Jordan
|
|
|
Grege *screened* Phone #: ###-####
|
BLD-Footing | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PART |
Mike Jordan
|
|
|
SCREENED late morning Jon Phone #: ###-####. No approved plans on site. Ok to place footing at contractors own risk. Will neeed to schedule a foundation inspection for concrete stemwall, have approved plans and paperwork on site to verify rear setback.
|