Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD95-00567
StatusFinaled
Name LANDER STREET SEWER PLANT
Site Address 790 N LANDER ST
Project Name 
Customer Number 
ePlanReviewNo
Description
ADDITION TO THE EXISTING OPERATION BUILDING * TO CONSTRUCT A NEW 3,667 SQ.FT. CAST IN PLACE CONCRETE MULTI-LEVEL HEADWORKS BUILDING. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED REQUIREMENT LIST, AND THE 1991 EDITION OF THE UBC. MP(#377-95) CU-9-95 INITIAL CERTIFICATE OF VALUE ON FILE ELEC 1,708,000 PLG.158,000 MEC 2,210,000 JOURNAL ENTRY FASBE NUMBER 9396202-22
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final2/4/19972/4/19972/4/1997PFAIL
DetailsCarl Dependahl
02/04/97 340 - left c/n, need all ok's, eng's ok, etc
INSP - Final1/30/19971/31/19971/31/1997ACANC
DetailsAlan Hauser
01/31/97 350 - to be done by #333
INSP - Final1/31/19971/31/19971/31/1997 FAIL
FINAL FAIL FIRE EXT LANDING AT EXIT DOOR EXIT SIGNS MANUAL FLUSH BOLTS ON 4 EXIT DOUBLE DOORS
INSP - Foundation11/27/199611/27/199611/27/1996PPART
DetailsWes Worcester
structural slab
INSP - Foundation9/4/19969/5/19969/5/1996APART
DetailsWes Worcester
submitting engineering change and verification of design/cover
INSP - Foundation8/30/19969/3/19969/3/1996ANR
DetailsWes Worcester
NORTHWEST
INSP - Foundation8/23/19968/26/19968/26/1996PNR
DetailsWes Worcester
INSP - Foundation8/26/19968/26/19968/26/1996PPART
DetailsWes Worcester
placing dobbies and cleaning out loose soil under rebar no transfer of special inspection process through City
INSP - Foundation8/26/19968/26/19968/26/1996PFAIL
DetailsWes Worcester
inadequate cover under #7 bar and not to resubmitted print as #5 mat not placed
INSP - Footings8/23/19968/23/19968/23/1996PNR
DetailsWes Worcester
this permit says it done is it realy?????? NOT REALLY>>>>CHECK DUPLICATE ERRONEOUS ENTRIES AND COMMERICIAL DOES NOT GET A LETTER OF COMPLIANCE !!!!!!
INSP - Conference8/5/19968/5/19968/5/1996APART
DetailsWes Worcester
met w/M Philips and he requested site inspection
INSP - Site Preparation8/5/19968/5/19968/5/1996APART
DetailsWes Worcester
noted area of change order as requested by plan ck
INSP - Conference7/31/19967/31/19967/31/1996APASS
DetailsWes Worcester
discussed masonry ties for rebar
INSP - Masonry7/31/19967/31/19967/31/1996APASS
DetailsWes Worcester
INSP - Swimming pool7/30/19967/31/19967/31/1996PCANC
DetailsWes Worcester
pool rebar could not find pool
INSP - Foundation5/29/19965/30/19965/24/1996PPART
DetailsWes Worcester
05/29/96 342 -
INSP - Foundation5/23/19965/24/19965/18/1996ANR
DetailsWes Worcester
05/23/96 342 - FND.REBAR CONTRACTORS NOWTHWEST IS THE ONE WHO CALLED.
INSP - Foundation5/18/19965/18/19965/18/1996 PASS
DetailsWes Worcester
/ / 342 - rebar at Americana for a weir
INSP - Foundation5/15/19965/16/19965/11/1996PNR
DetailsWes Worcester
05/15/96 342 -
INSP - Foundation5/8/19965/9/19965/3/1996APART
DetailsWes Worcester
05/08/96 342 - REBAR..CONTRACTOR NORTHWEST
INSP - Footings5/2/19965/6/19964/30/1996APART
DetailsWes Worcester
05/06/96 342 - appointment for 8:30 to 9 a.m.
INSP - Footings4/25/19964/26/19964/20/1996AFAIL
DetailsWes Worcester
04/25/96 342 - SLAB cover, add bar not done, conduit tied to bar
INSP - Foundation4/24/19964/25/19964/20/1996PNR
DetailsWes Worcester
04/25/96 342 - FLOOR SLAB..FRI PM
INSP - Flatwork4/20/19964/20/19964/20/1996 PART
DetailsWes Worcester
/ / 342 -
INSP - Flatwork4/20/19964/20/19964/20/1996 FAIL
DetailsWes Worcester
/ / 342 - cover inadequate, rebar tied to conduit, added bar not corre
INSP - Flatwork4/19/19964/19/19964/19/1996 FAIL
DetailsWes Worcester
/ / 342 - late pm thurs min cover lacking at forms and around conduit. still adding added bar. N
INSP - Foundation4/11/19964/11/19964/11/1996PPASS
Details
FND. REBAR main pump room at east side
INSP - Foundation4/10/19964/11/19964/11/1996APASS
Details
REBAR
INSP - Foundation4/8/19964/9/19964/9/1996APASS
DetailsWes Worcester
REBAR
INSP - Foundation4/2/19964/3/19963/30/1996ACANC
DetailsWes Worcester
04/02/96 342 - REBAR
INSP - Foundation4/3/19964/3/19963/30/1996PNR
DetailsWes Worcester
04/03/96 342 - FND.REBAR.
INSP - Foundation3/30/19963/30/19963/30/1996 PART
DetailsWes Worcester
/ / 342 - slab pour ok, Eric to check clearance of side boards not yet
INSP - Foundation3/28/19963/28/19963/24/1996PFAIL
DetailsWes Worcester
03/28/96 342 - SLAB REBAR change of design and deletion of a beam from approved plan. resubmit cha in duplicate with engineering. do not cover rebar
INSP - Foundation3/19/19963/19/19963/19/1996PPART
DetailsWes Worcester
WALLS - REBAR special inspector on site
INSP - Foundation3/18/19963/18/19963/14/1996PNR
DetailsWes Worcester
03/18/96 342 - spec insp on site, not ready earlier
INSP - Foundation3/13/19963/13/19963/13/1996PPART
DetailsWes Worcester
fnd.rebar looked ok what was done, special insp on site
INSP - Flatwork3/7/19963/7/19963/7/1996PPASS
DetailsWes Worcester
SLAB REBAR INSP. ok and special inspector on site
INSP - Foundation3/5/19963/5/19963/5/1996PNR
DetailsWes Worcester
REBAR not done ck back 03/06/96 in am
INSP - Foundation3/1/19962/29/19963/1/1996APASS
DetailsWes Worcester
INSP - Foundation2/28/19962/29/19962/29/1996ANR
DetailsWes Worcester
REBAR not ready will be back at 10 am 03/01/96
INSP - Foundation2/16/19962/16/19962/16/1996PPART
DetailsWes Worcester
SPECIAL INSP. ON SITE.
INSP - Foundation2/15/19962/15/19962/15/1996ANR
DetailsWes Worcester
inadequate cover, special inspector on site
INSP - Foundation2/14/19962/14/19962/14/1996PNR
DetailsWes Worcester
fnd.rebar spec insp on site
INSP - Conference2/13/19962/13/19962/13/1996 FAIL
called Joel asking for engineer's report on masonry wall
INSP - Conference2/12/19962/12/19962/12/1996 FAIL
could not find Joel RE: Engineer's report on masonry const
INSP - Conference2/8/19962/9/19962/9/1996 PART
poured 2nd section of clarifier w/spec insp on site
INSP - Foundation2/5/19962/6/19962/6/1996APASS
Details
02/05/96 338 -
INSP - Foundation1/31/19962/1/19962/1/1996APART
DetailsWes Worcester
REBAR pouring and notified spec insp of difficulty w/tremmie
INSP - Foundation1/16/19961/17/19961/17/1996ANR
DetailsWes Worcester
01/16/96 342 - FND.REBAR still have clearance problems
INSP - Masonry1/17/19961/17/19961/17/1996 PART
DetailsWes Worcester
/ / 342 - spec insp on site but was only going to look at 3000 psi con
INSP - Footings1/11/19961/11/19961/11/1996 PART
DetailsWes Worcester
/ / 342 - poured last 1/4 of clarifier w/special insp on site. log and
INSP - Foundation1/11/19961/11/19961/11/1996PFAIL
DetailsWes Worcester
01/11/96 342 - ftg, stem wall & slab poured or being poured w/o approval Report pending as well as engineers design and acceptance..2 story CMU blding next to raceway. Notified Joel and Jim Cox. No ftg or brng earth
INSP - Foundation1/11/19961/11/19961/11/1996 PART
DetailsWes Worcester
/ / 342 - special insp on site for walls west of clarifier. log and re
INSP - Foundation1/11/19961/11/19961/11/1996 PART
DetailsWes Worcester
/ / 342 - wall west of clarifier
INSP - Conference1/10/19961/10/19961/10/1996 PART
DetailsWes Worcester
/ / 342 - Discussed special insp process, min cover and min code compl will have min code compliance and if deficient const is found again I wi stop const until deficiency is corrected. We will have final acceptance, irregardless what the sp
INSP - Footings1/10/19961/10/19961/10/1996 FAIL
DetailsWes Worcester
/ / 342 - for 2 story addn over slurry and conduit. no epoxy in drille
INSP - Footings1/10/19961/10/19961/10/1996 PART
DetailsWes Worcester
/ / 342 - For 2nd story poured w/o insp., require letter from engineer is ok.. Notified Joel, Jim, and Eric.
INSP - Foundation1/10/19961/10/19961/10/1996 PART
DetailsWes Worcester
/ / 342 - 2nd story poured w/special insp on site
INSP - Foundation1/9/19961/10/19961/10/1996ANR
DetailsWes Worcester
01/10/96 342 - REBAR
INSP - Foundation1/8/19961/8/19961/8/1996PPART
DetailsWes Worcester
waiting on engineering for masonry wall not on a ftg or brng earth
INSP - Footings1/5/19961/5/19961/5/1996 FAIL
DetailsWes Worcester
/ / 342 - footings for 2nd story addn not ready and is over electrical super of concerns and will ck bk later
INSP - Footings1/4/19961/5/19961/5/1996AFAIL
DetailsWes Worcester
01/05/96 342 - not ready... no epoxy on rebar in 3" hole into old cement
INSP - Conference1/4/19961/4/19961/4/1996 PASS
DetailsWes Worcester
/ / 342 - With Bob from CNI home office (owner) about special inspecti Maintained plan check criteria and we will get minimum code compliance
INSP - Foundation1/3/19961/4/19961/4/1996ANR
DetailsWes Worcester
01/03/96 342 - rebar foundation
INSP - Foundation1/4/19961/4/19961/4/1996 PASS
DetailsWes Worcester
/ / 342 - c/n removed as spec insp submitting report
INSP - Foundation12/28/199512/28/19951/4/1996PFAIL
DetailsWes Worcester
12/28/95 342 - c/n issued re: spec insp not on site, 2" of cover needed and no concern demostrated by individuals on site. Notified super
INSP - Footings12/21/199512/21/199512/21/1995PPART
DetailsWes Worcester
12/21/95 342 - THIS WAS CALLED IN FOR THE 20TH. POURED W/ SPECIAL INSP ON SITE
INSP - Footings12/21/199512/21/199512/21/1995PPART
DetailsJim Sly
THIS WAS CALLED IN FOR YESTERDAY. spec insp to be on site
INSP - Foundation12/18/199512/18/199512/19/1995PPART
DetailsWes Worcester
12/18/95 342 - rebar without adequate cover, Joel will have pad regraded
INSP - Footings12/8/199512/8/199512/8/1995PPART
DetailsWes Worcester
12/08/95 342 - SPECIAL INSPECTORS ON JOB..... poured
INSP - Foundation11/27/199511/28/199511/28/1995AFAIL
Details
FND.REBAR cover inadequate
INSP - Carpentry11/20/199511/20/199511/20/1995PPART
DetailsWes Worcester
/ / 342 - rebar insp.
INSP - Conference11/17/199511/16/199511/16/1995 PART
DetailsJim Sly
INSP - Conference11/16/199511/16/199511/16/1995PNR
DetailsWes Worcester
11/16/95 342 - MEETING AT 3PM.
INSP - Footings11/15/199511/15/199511/15/1995PPART
DetailsJim Sly
REBAR spec insp to be on site
INSP - Foundation10/31/199511/2/199511/2/1995AFAIL
DetailsJim Sly
cover inadequate
INSP - Footings11/1/199511/1/199511/1/1995 FAIL
INSP - Foundation10/31/199511/1/199511/1/1995AFAIL
DetailsJim Sly
REBAR
INSP - Foundation1/25/19961/26/19961/26/1995APART
DetailsWes Worcester
poured FND.REBAR inspected w/special inspector on site.