Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD95-00907
StatusFinaled
Name TREASURE VALLEY HOSPITAL
Site Address 8800 W EMERALD ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct the structural shell of 28,828 sq. ft. and then finish the interior areas, except the Physical Therapy Suite, for use as Treasure Valley Hospital per the approved plans. To comply with requirements for a fully fire sprinklered, Type II-FR, noncombustible, fire-resistive building. To create operating rooms, patient rooms and support areas as shown on the plans. Contact person is Marv Meyers, Russell Corp. @ 323-0777. Separate elect., mech. & plumbing permits are required. DR-20-94, CU-6-94 PC320-94 drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Occupancy Sign-off10/17/199610/18/199610/18/1996APASS
DetailsJoe Tawney
10/18/96 406 - sign off for perm occ
Permanent Occupancy 10/18/199610/18/1996 DONE
Details
INSP - Final9/25/19969/25/19969/25/1996 PASS
OK FOR TEMP OCC REINSPECTION REQ
INSP - Framing/Rough-in8/15/19968/16/19968/16/1996APASS
Details
08/15/96 338 -
INSP - Framing/Rough-in8/1/19968/1/19968/1/1996PPART
Details
Reviewed suspended ceiling in corridors #1161 & 1166 lights require wires some misc. penetrations reguire firecaulk also reviewed and approved sheetrock ceiling cover in dietary room, walls @ mechanical room and corridor in this area are not completely firecaulked, will need to reinspect penetrations through ceiling access. 325.
INSP - Framing/Rough-in6/26/19966/27/19966/27/1996APASS
Details
06/26/96 338 - lead lining complete
INSP - Framing/Rough-in6/6/19966/6/19966/6/1996PPART
Details
06/06/96 338 - partial penetration protection assemblies check
INSP - Framing/Rough-in5/22/19965/23/19965/23/1996APASS
Details
05/23/96 338 - AM. THURS. made ok ok to cover walls behind the elec plm need to inspect the firecaulk at the penetrations above the ceiling line before ceilings are installed.
INSP - Framing/Rough-in5/14/19965/15/19965/15/1996APART
Details
05/14/96 338 - partial made ok
INSP - Framing/Rough-in4/30/19965/1/19965/1/1996APART
Details
04/30/96 338 - partial ok to cover
INSP - Framing/Rough-in4/29/19964/30/19964/30/1996APART
Details
04/29/96 338 -
INSP - Framing/Rough-in3/20/19963/20/19963/20/1996PPART
Details
03/20/96 338 - fire proofing inspN
INSP - Carpentry3/12/19963/12/19963/12/1996PPASS
Details
03/12/96 338 - FIREPROOFING PAR T MADE K
INSP - Conference2/16/19962/16/19962/15/1996PPASS
Details
02/16/96 338 - MIKE WILL CALL YOU FOR A TIME.
INSP - Flatwork2/7/19962/7/19962/7/1996PPASS
Details
02/07/96 333 - slab FRMS-OK FORMS-REBAR
INSP - Roof1/26/19961/29/19961/29/1996APASS
Details
01/29/96 333 - framing of roof ok pending special inspection reports
INSP - Carpentry1/9/19961/10/19961/10/1996APASS
Details
01/09/96 333 - MTC ALREADY INSPECTED - FLOOR POUR (ROOF) POURING THURSDA FRMS-OK FORMS-REBAR for roof floor future expansion
INSP - Footings11/22/199511/22/199511/22/1995PPART
DetailsCarl Dependahl
11/22/95 340 - REBAR ALSO
INSP - Footings11/20/199511/21/199511/21/1995PPASS
Details
11/21/95 333 - REBAR FTG -OK FOOTING
INSP - Carpentry11/20/199511/20/199511/20/1995PPASS
Details
11/20/95 333 - rebar FTG -OK FOOTING grade beams
INSP - Foundation11/17/199511/17/199511/20/1995PPASS
Details
11/17/95 333 - REBAR & CONCRETE FDN -OK FOUNDATION
INSP - Foundation11/16/199511/16/199511/16/1995PPASS
Details
11/16/95 333 - FTG -OK FOOTING
INSP - Foundation11/1/199511/2/199511/2/1995APASS
Details
11/01/95 333 - FTG -OK FOOTING
INSP - Footings10/19/199510/19/199510/19/1995 PASS
Details
/ / 333 - FTG -OK FOOTING
INSP - Footings10/16/199510/17/199510/17/1995APART
Details
10/17/95 338 - REBAR THEY ARE USING SPECIAL INSPECTORS. POURED W/O INSP