Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD95-01438
StatusFinaled
Name ACCESSIBLE SPACE INC
Site Address 5306 W STATE ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To build a 24,182 SF (24 UNIT) three story, barrier free, Apartment building with elevator, lobbies, mechanical, maintenance, refuse/recycle, offices, lounge, laundry, game room, library, and community room per approved plans and attached requirement list. Design Review # DR-76-94. CU-41-94. PLAN CHECK # 634-95. A separate Plumbing, Mechanical, and Electrical Permit must be obtained to complete this project. A new Certificate of Occupancy must be obtained by owner prior to occupying the building. THIS BUILDING IS FULLY FIRE SPRINKLERED. PRP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final6/11/19976/12/19976/12/1997PPASS
DetailsJoe Tawney
06/12/97 406 - FIRE ALARM REINSPECT FOR FINAL REINSP FOR FINAL OK FOR PERM OCC
INSP - Final6/12/19976/12/19976/12/1997 PASS
DetailsAlan Hauser
/ / 350 - signed occ. card final
Permanent Occupancy 6/12/19976/12/1997 DONE
Details
Permanent Occupancy 6/12/19976/12/1997 DONE
Details
INSP - Final6/9/19976/9/19976/9/1997 PART
DetailsAlan Hauser
/ / 350 - meet with fire inspector (joe), went through the building, n corrections, some on fire side. no temp. occ.
INSP - Final6/6/19976/9/19976/9/1997PNR
DetailsCarl Dependahl
06/09/97 340 - IS MEETING JOE AT 1 O'CLOCK (CARL---PLEASE LET THEM KNOW FOR PLUMBING.....THANKS LINDA)
INSP-Final Inspection6/6/19976/9/19976/9/1997PFAIL
DetailsJoe Tawney
06/09/97 406 - WOULD LIKE IT 1 O'CLOCK PER YOU FINAL FAIL DETECTOR IN ELEV SHAFT STROBES TO BE 15 FT FROM END OF HALL HI INTENSITY STROBE IN HEARING IMP ROOM FIRE EXT NEED TAGS
INSP-Sprinkler Rough-in/Hydro6/6/19976/9/19976/9/1997PPASS
DetailsJoe Tawney
06/09/97 406 - 1 O'CLOCK PER YOU I GEUSS FINAL ON SPKLR SYSTEMS OK FOR PERM OCC
INSP-Sprinkler Rough-in/Hydro5/19/19975/20/19975/20/1997ACANC
DetailsJoe Tawney
05/20/97 406 - AFTER 10:00 spklr test for final cancelled until 5/21/97
INSP-Sprinkler Rough-in/Hydro5/5/19975/6/19975/6/1997PPART
DetailsJoe Tawney
OK ON HYDRO TEST FOR WP AND DP SYSTEMS ALSO AIR TEST ON DP SYSTEM
INSP-Conference4/2/19974/2/19974/2/1997 PASS
CONF WITH SIMPLEX TOM KYLE ON ALARM SYSTEM FOR THIS BLDG
INSP - Framing/Rough-in3/26/19973/27/19973/26/1997AFAIL
Details
03/27/97 333 - FRAME REINSEPCT OTH-OTHER AGENCIES NOT APPROVED
INSP - Framing/Rough-in3/20/19973/21/19973/20/1997PFAIL
Details
03/21/97 333 - 1ST FLOOR CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP-Sprinkler Rough-in/Hydro3/19/19973/20/19973/20/1997APART
DetailsJoe Tawney
03/20/97 406 - call before going pager ###-#### rick ROUGH IN OK TO COVER FIRST FLOOR
INSP-Sprinkler Rough-in/Hydro3/11/19973/12/19973/12/1997PPART
DetailsJoe Tawney
03/12/97 406 - RICK - PAGER ###-#### OK ON UNDERGROUND HYDRO TEST
INSP-Conference3/6/19973/6/19973/6/1997 PASS
DetailsJoe Tawney
/ / 406 - CONF WITH PAUL OF ASI ADV 2ND HYD REQ AT NORTH END OF PROPER ALSO ADV SUBMITTAL REQ FOR ALARM SYSTEM
INSP-Sprinkler Rough-in/Hydro3/5/19973/6/19973/6/1997APART
DetailsJoe Tawney
03/06/97 406 - RICK - PAGER ###-#### SPKLR ROUGH IN FOR 2ND FLOOR OK TO COVER
INSP - Conference3/5/19973/5/19973/5/1997 PASS
DetailsAlan Hauser
/ / 350 - TALKED WITH CONTRACTOR ABOUT FIRE HYD. AND WENT OVER FIRE BL FLR.
INSP - Conference2/24/19972/24/19972/24/1997 PASS
DetailsAlan Hauser
/ / 350 - conf. on 3 rd floor ceiling, ok to start to insulate attic
INSP - Conference2/20/19972/20/19972/20/1997 PASS
DetailsAlan Hauser
/ / 350 - went over 3rd flr. heating
INSP-Sprinkler Rough-in/Hydro2/20/19972/20/19972/20/1997PPART
DetailsJoe Tawney
02/20/97 406 - RICK - ###-#### spklr rough in OK TO COVER 3RD FLOOR
INSP - Conference2/7/19972/7/19972/7/1997 PASS
DetailsAlan Hauser
/ / 350 - went over 3rd floor with framers, htg, elec. on fire blockin stopping requirements
INSP - Conference1/28/19971/28/19971/28/1997 PASS
DetailsAlan Hauser
/ / 350 - WENT OVER INFORMATION FROM FIRE SPRINKLER CONTRACTOR ON PIPE PROTECTIONS IN 1 HR. WALL/CORRIDORS
INSP - Conference1/24/19971/24/19971/24/1997 PASS
DetailsAlan Hauser
/ / 350 - left corrections notice with supt. about plastic sprinkler p at corridor walls. need detail on protection
INSP - Conference1/16/19971/16/19971/16/1997 PASS
DetailsAlan Hauser
/ / 350 - left notice on clarification on laundry room rated wall, det
INSP - Conference1/14/19971/14/19971/14/1997 PASS
DetailsAlan Hauser
/ / 350 - conf. with builder, electrican, plbg, and bob a. about fire requirements.
INSP - Conference1/10/19971/10/19971/10/1997 PASS
DetailsAlan Hauser
/ / 350 - talked with supt. about fire caulking and setting up a meeti supervisior
INSP - Conference1/10/19971/10/19971/10/1997 PASS
DetailsAlan Hauser
/ / 350 - talked to bob a. about a meeting with supt. of job next wed. caulking.
INSP - Framing/Rough-in12/30/19961/2/19971/2/1997APASS
DetailsAlan Hauser
01/02/97 350 - shearwall nailing of 1st floor exterior and interior shea
INSP - Conference12/16/199612/16/199612/16/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. WITH FRAMER, BUILDER, AND PLBG. ABOUT PARTY WALLS AND PROTECTION AT CEILING/FLOOR ASSEMBLY FOR 1 HR.
INSP - Foundation11/14/199611/14/199611/14/1996PPASS
DetailsAlan Hauser
11/14/96 350 - INSPECTION OF REBAR IN STEM WALLS, REBAR AS PER PLAN
INSP - Footings11/13/199611/13/199611/13/1996PPASS
DetailsAlan Hauser
11/13/96 350 - THIS HAS SPECIAL INSPECTIONS, ALSO LOOKED AT FTNS. FTNS A