INSP - Final | 6/11/1997 | 6/12/1997 | 6/12/1997 | P | PASS |
Joe Tawney
|
|
|
06/12/97 406 - FIRE ALARM REINSPECT FOR FINAL REINSP FOR FINAL OK FOR PERM OCC
|
INSP - Final | 6/12/1997 | 6/12/1997 | 6/12/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - signed occ. card final
|
Permanent Occupancy | | 6/12/1997 | 6/12/1997 | | DONE |
|
|
|
|
Permanent Occupancy | | 6/12/1997 | 6/12/1997 | | DONE |
|
|
|
|
INSP - Final | 6/9/1997 | 6/9/1997 | 6/9/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - meet with fire inspector (joe), went through the building, n corrections, some on fire side. no temp. occ.
|
INSP - Final | 6/6/1997 | 6/9/1997 | 6/9/1997 | P | NR |
Carl Dependahl
|
|
|
06/09/97 340 - IS MEETING JOE AT 1 O'CLOCK (CARL---PLEASE LET THEM KNOW FOR PLUMBING.....THANKS LINDA)
|
INSP-Final Inspection | 6/6/1997 | 6/9/1997 | 6/9/1997 | P | FAIL |
Joe Tawney
|
|
|
06/09/97 406 - WOULD LIKE IT 1 O'CLOCK PER YOU FINAL FAIL DETECTOR IN ELEV SHAFT STROBES TO BE 15 FT FROM END OF HALL HI INTENSITY STROBE IN HEARING IMP ROOM FIRE EXT NEED TAGS
|
INSP-Sprinkler Rough-in/Hydro | 6/6/1997 | 6/9/1997 | 6/9/1997 | P | PASS |
Joe Tawney
|
|
|
06/09/97 406 - 1 O'CLOCK PER YOU I GEUSS FINAL ON SPKLR SYSTEMS OK FOR PERM OCC
|
INSP-Sprinkler Rough-in/Hydro | 5/19/1997 | 5/20/1997 | 5/20/1997 | A | CANC |
Joe Tawney
|
|
|
05/20/97 406 - AFTER 10:00 spklr test for final cancelled until 5/21/97
|
INSP-Sprinkler Rough-in/Hydro | 5/5/1997 | 5/6/1997 | 5/6/1997 | P | PART |
Joe Tawney
|
|
|
OK ON HYDRO TEST FOR WP AND DP SYSTEMS ALSO AIR TEST ON DP SYSTEM
|
INSP-Conference | 4/2/1997 | 4/2/1997 | 4/2/1997 | | PASS |
|
|
|
CONF WITH SIMPLEX TOM KYLE ON ALARM SYSTEM FOR THIS BLDG
|
INSP - Framing/Rough-in | 3/26/1997 | 3/27/1997 | 3/26/1997 | A | FAIL |
|
|
|
03/27/97 333 - FRAME REINSEPCT OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Framing/Rough-in | 3/20/1997 | 3/21/1997 | 3/20/1997 | P | FAIL |
|
|
|
03/21/97 333 - 1ST FLOOR CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Sprinkler Rough-in/Hydro | 3/19/1997 | 3/20/1997 | 3/20/1997 | A | PART |
Joe Tawney
|
|
|
03/20/97 406 - call before going pager ###-#### rick ROUGH IN OK TO COVER FIRST FLOOR
|
INSP-Sprinkler Rough-in/Hydro | 3/11/1997 | 3/12/1997 | 3/12/1997 | P | PART |
Joe Tawney
|
|
|
03/12/97 406 - RICK - PAGER ###-#### OK ON UNDERGROUND HYDRO TEST
|
INSP-Conference | 3/6/1997 | 3/6/1997 | 3/6/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF WITH PAUL OF ASI ADV 2ND HYD REQ AT NORTH END OF PROPER ALSO ADV SUBMITTAL REQ FOR ALARM SYSTEM
|
INSP-Sprinkler Rough-in/Hydro | 3/5/1997 | 3/6/1997 | 3/6/1997 | A | PART |
Joe Tawney
|
|
|
03/06/97 406 - RICK - PAGER ###-#### SPKLR ROUGH IN FOR 2ND FLOOR OK TO COVER
|
INSP - Conference | 3/5/1997 | 3/5/1997 | 3/5/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - TALKED WITH CONTRACTOR ABOUT FIRE HYD. AND WENT OVER FIRE BL FLR.
|
INSP - Conference | 2/24/1997 | 2/24/1997 | 2/24/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - conf. on 3 rd floor ceiling, ok to start to insulate attic
|
INSP - Conference | 2/20/1997 | 2/20/1997 | 2/20/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - went over 3rd flr. heating
|
INSP-Sprinkler Rough-in/Hydro | 2/20/1997 | 2/20/1997 | 2/20/1997 | P | PART |
Joe Tawney
|
|
|
02/20/97 406 - RICK - ###-#### spklr rough in OK TO COVER 3RD FLOOR
|
INSP - Conference | 2/7/1997 | 2/7/1997 | 2/7/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - went over 3rd floor with framers, htg, elec. on fire blockin stopping requirements
|
INSP - Conference | 1/28/1997 | 1/28/1997 | 1/28/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - WENT OVER INFORMATION FROM FIRE SPRINKLER CONTRACTOR ON PIPE PROTECTIONS IN 1 HR. WALL/CORRIDORS
|
INSP - Conference | 1/24/1997 | 1/24/1997 | 1/24/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - left corrections notice with supt. about plastic sprinkler p at corridor walls. need detail on protection
|
INSP - Conference | 1/16/1997 | 1/16/1997 | 1/16/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - left notice on clarification on laundry room rated wall, det
|
INSP - Conference | 1/14/1997 | 1/14/1997 | 1/14/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - conf. with builder, electrican, plbg, and bob a. about fire requirements.
|
INSP - Conference | 1/10/1997 | 1/10/1997 | 1/10/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - talked with supt. about fire caulking and setting up a meeti supervisior
|
INSP - Conference | 1/10/1997 | 1/10/1997 | 1/10/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - talked to bob a. about a meeting with supt. of job next wed. caulking.
|
INSP - Framing/Rough-in | 12/30/1996 | 1/2/1997 | 1/2/1997 | A | PASS |
Alan Hauser
|
|
|
01/02/97 350 - shearwall nailing of 1st floor exterior and interior shea
|
INSP - Conference | 12/16/1996 | 12/16/1996 | 12/16/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - CONF. WITH FRAMER, BUILDER, AND PLBG. ABOUT PARTY WALLS AND PROTECTION AT CEILING/FLOOR ASSEMBLY FOR 1 HR.
|
INSP - Foundation | 11/14/1996 | 11/14/1996 | 11/14/1996 | P | PASS |
Alan Hauser
|
|
|
11/14/96 350 - INSPECTION OF REBAR IN STEM WALLS, REBAR AS PER PLAN
|
INSP - Footings | 11/13/1996 | 11/13/1996 | 11/13/1996 | P | PASS |
Alan Hauser
|
|
|
11/13/96 350 - THIS HAS SPECIAL INSPECTIONS, ALSO LOOKED AT FTNS. FTNS A
|