Permit Information
Permit NumberBLD95-01678
StatusFinaled
Name 1ST PRESBYTERIAN CHURCH
Site Address 950 W STATE ST
Project Name 
Customer Number 
ePlanReviewNo
Description
**FIRST PRESBYTERIAN CHURCH** --Terrance L. Butler is the Architect of record.-- This building is to be fire sprinkled in phases. The fire sprinkler system substitutes for 1-hr fire-resistive construction. To remodel and renovate an existing church building. Phases II and III are covered under this permit. Work is generally within the Christian Education "Building" and includes a new elevator, 1-hr stair enclosure, 1-hr corridors, an additional exit stairway from the first floor, and new openings to the Lindsay Hall all per approved drawings, engineering, and plan check notes on file. The C.E.B. first floor is being converted to a Day Care (E-3). Separate electrical, plumbing, and mechanical permits are required. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. SPECIAL INSPECTION IS REQUIRED FOR WELDING, CONCRETE, AND UNDERPINNING OF THE EXISTING FOUNDATIONS. PC-686-95 **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final6/20/19966/21/19966/21/1996APART
DetailsWes Worcester
FRI. LATE A.M. TEMPORARY OK, FINAL OK, ELELVATOR OK
INSP - Final6/21/19966/21/19966/21/1996 PART
DetailsWes Worcester
06/21/96 342 - FRI. LATE A.M.
Permanent Occupancy 6/21/19966/21/1996 DONE
Details
INSP - Final6/7/19966/7/19966/7/1996PPART
DetailsWes Worcester
06/07/96 342 -
INSP - Final6/5/19966/5/19966/5/1996PNR
DetailsWes Worcester
06/05/96 342 - THIS IS THE ONE YOU DID THIS A.M.
INSP - Final5/30/19965/30/19965/30/1996 NR
DetailsWes Worcester
/ / 342 -
INSP - Final6/4/19966/4/19965/29/1996PNR
DetailsWes Worcester
06/04/96 342 - 3 P.M. APPOINTMENT
INSP - Final5/30/19965/31/19965/25/1996PNR
DetailsWes Worcester
05/31/96 342 - FRI. P.M.
INSP - Ceiling grid5/24/19965/24/19965/18/1996PNH
DetailsWes Worcester
05/24/96 342 -
INSP - Ceiling grid5/15/19965/16/19965/11/1996PCANC
DetailsWes Worcester
05/15/96 342 - This is for a suspended ceiling inspection. Wes sick
INSP - Conference5/10/19965/10/19965/4/1996PPASS
DetailsWes Worcester
05/10/96 342 - met w/architect and he is to advise contractor of fix for
INSP - Carpentry4/8/19964/9/19964/9/1996APASS
DetailsWes Worcester
INSP - Footings4/1/19964/2/19963/30/1996APASS
DetailsWes Worcester
04/02/96 342 - EARLY A.M. PLEASE partial in basement
INSP - Footings3/20/19963/21/19963/21/1996APART
DetailsWes Worcester
LATE AM PLEASE 1st 8' and adjoining ftg
INSP - Footings3/18/19963/19/19963/15/1996APASS
DetailsWes Worcester
03/18/96 342 - EARLY TUES.A.M. FLOOR FOOTING....ELEVATOR PIT...... rebar ok. retaining wall awaiting engineering.
INSP - Ceiling grid3/14/19963/15/19963/11/1996APART
DetailsWes Worcester
03/15/96 342 - only two rooms ready, will look at remainder next week
INSP - Framing/Rough-in3/7/19963/8/19963/8/1996PPART
DetailsWes Worcester
Lindsey corridor and a portion of all others ok after plumb insp
INSP - Foundation2/26/19962/27/19962/27/1996PNR
DetailsWes Worcester
LATE PM. FND. WALL not ready, ck back 02/28 at 1 pm. Note they have changed elevator ftgs. and grade beam brng.
INSP - Carpentry2/15/19962/16/19962/16/1996ANR
DetailsWes Worcester
INSP - Framing/Rough-in1/31/19961/31/19961/31/1996PPART
DetailsWes Worcester
outside corridor
INSP - Framing/Rough-in1/26/19961/26/19961/26/1996PPART
DetailsWes Worcester
corridor wall ok, and has been changed since conference when it was noted that there was not a continous membrane at wall
INSP - Carpentry1/24/19961/24/19961/24/1996 PASS
DetailsWes Worcester
/ / 342 - 1 hr wall is incorrect. Correcting
INSP - Flatwork1/24/19961/24/19961/24/1996PCANC
DetailsWes Worcester
01/24/96 342 - no insp required
INSP - Foundation1/22/19961/23/19961/24/1996APASS
DetailsWes Worcester
01/23/96 342 - FND. STEM WALLS.
INSP - Footings1/19/19961/22/19961/22/1996APASS
DetailsWes Worcester
01/19/96 342 -