Permit Information
Permit NumberBLD96-00164
StatusFinaled
Name MIDDLETON WILLIAM C
Site Address 5485 N GARY LN
Project NameGLENBROOK TOWNHOUSES
Customer Number 
ePlanReviewNo
Description
To build a new four unit apartment building to the standards of Townhouses for future conversion as per approved plans on file. A Separate Electrical, Plumbing, and Mechanical Permit is required for this project. CU-53-95. Plan Check # 036-96. PRP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Wall cover9/18/19969/18/19969/18/1996PPASS
DetailsAlan Hauser
09/18/96 350 - shear nailing ok talked to plumber about plumbing in 1 hr
INSP - Foundation8/22/19968/23/19968/23/1996PPASS
DetailsAlan Hauser
08/23/96 350 - SETBACKS AS PER PLAN REBAR HAS PROPER COVER HORIZONTALS O
INSP - Foundation7/29/19967/30/19967/30/1996APASS
DetailsAlan Hauser
07/30/96 350 - stem walls ok rebar has proper cover
INSP - Foundation7/24/19967/24/19967/24/1996PPASS
DetailsAlan Hauser
07/24/96 350 - FOOTINGS OK REBAR HAS PROPER COVER
INSP - Final7/19/19967/19/19967/19/1996PPASS
DetailsAlan Hauser
07/19/96 350 - final ok
INSP - Letter of compliance7/19/19967/19/19967/19/1996 PASS
DetailsAlan Hauser
/ / 350 - C/C#11467
INSP - Letter of compliance7/19/19967/19/19967/19/1996 PASS
DetailsAlan Hauser
/ / 350 - C/C#11467
INSP - Framing/Rough-in7/15/19967/16/19967/16/1996APASS
DetailsJim Sly
07/15/96 316 - FLOOR
INSP - Framing/Rough-in7/11/19967/11/19967/11/1996PPASS
DetailsMike Jordan
07/11/96 50 - sub-floor UNDERFLOOR INSPECTION OK NEED TO REMOVE INSULATION FROM VENTILATION OPEN AND FINISH HEADERS AND TRIMMERS AT CRAWL OPENINGS
INSP - Foundation5/30/19965/30/19965/30/1996PPASS
DetailsJim Sly
05/30/96 316 -
INSP - Foundation5/23/19965/24/19965/24/1996APASS
DetailsJim Sly
05/23/96 316 -
INSP - Foundation5/13/19965/14/19965/14/1996APASS
DetailsJim Sly
05/13/96 316 -
INSP - Foundation5/8/19965/9/19965/9/1996APASS
DetailsJim Sly
05/08/96 316 -
INSP - Footings4/25/19964/26/19964/26/1996APASS
DetailsJim Sly
04/25/96 316 - Footings and stem walls on 2nd bldg...need new permit #.
INSP - Framing/Rough-in4/19/19964/22/19964/22/1996APASS
DetailsJim Sly
04/19/96 316 - SHEAR WALL Extend sheathing down to attach to mud sill... shear wall panels OK.
INSP - Carpentry4/2/19964/2/19964/2/1996 PASS
DetailsJim Sly
/ / 316 - Last townhouse wall inspection for 4 units adjacent to Gary lane.
INSP - Wall cover4/2/19964/2/19964/2/1996PCANC
DetailsJim Sly
04/02/96 316 - DRY WALL NAILING. Inspected AM.
INSP - Carpentry3/27/19963/27/19963/27/1996PPASS
DetailsJim Sly
03/27/96 316 - FIREWALL Townhouse wall inspection...Partial..1st bldg. 1/2 of (2) walls...East end. OK
INSP - Framing/Rough-in3/13/19963/14/19963/14/1996PPASS
DetailsJim Sly
03/14/96 316 - FRAMING SUB-FLOOR ...OK Sub floor inspection complete.
INSP - Foundation3/11/19963/12/19963/12/1996APASS
DetailsJim Sly
Stem wall re-bar OK ...West side of Bldg. (1st bldg.)
INSP - Framing/Rough-in3/8/19963/11/19963/11/1996ACANC
DetailsJim Sly
transfer to 401.
INSP - Framing/Rough-in3/11/19963/11/19963/11/1996APASS
Details
subfloor
INSP - Framing/Rough-in3/7/19963/8/19963/8/1996ACANC
DetailsJim Sly
SUB-FLOOR FRAMING Cancelled.
INSP - Footings3/7/19963/7/19963/7/1996PPASS
DetailsJim Sly
All footings under this permit now inspected and OK as per Jim Sly and Wes.
INSP - Footings3/6/19963/7/19963/7/1996ANR
DetailsJim Sly
03/06/96 316 - Not ready
INSP - Footings3/4/19963/6/19963/6/1996PFAIL
DetailsJim Sly
Correction notice...re-bar cover and possible pour over fill. Clean out loose material and call for re-inspection.
INSP - Foundation2/29/19962/29/19962/29/1996PPASS
DetailsJim Sly
INSP - Foundation2/26/19962/27/19962/27/1996APASS
DetailsJim Sly
Checked re-bar...OK.
INSP - Footings2/22/19962/23/19962/23/1996APASS
Details