INSP-Final Inspection | 5/8/1997 | 5/8/1997 | 5/8/1997 | P | PASS |
|
|
|
perm occupancy ok, storage plan approved per bld96-3198
|
INSP - Final | 3/3/1997 | 3/3/1997 | 3/3/1997 | P | PASS |
|
|
|
EARLY PM, REINSPECT FOR FINAL, GRINNEL TO CORRECT FDC THIS AM fdc corrected, keys still not in knox box......manager to do tuesday
|
INSP - Final | 2/28/1997 | 3/3/1997 | 3/3/1997 | P | PASS |
Jim Storey
|
|
|
03/03/97 301 - FINAL FOR C/O FNL -OK FINAL ì
|
Permanent Occupancy | | 3/3/1997 | 3/3/1997 | | DONE |
|
|
|
|
INSP - Final | 2/28/1997 | 2/28/1997 | 2/28/1997 | A | NR |
|
|
|
late recheck fdc & tank not ready at 10:30 am still not ready at 4:00pm
|
INSP - Final | 2/27/1997 | 2/27/1997 | 2/27/1997 | P | PART |
|
|
|
still need to rotate fdc and vent diesel tank
|
INSP - Occupancy Sign-off | 2/27/1997 | 2/27/1997 | 2/27/1997 | P | CANC |
Jim Storey
|
|
|
02/27/97 301 - CANCLED BY CONTRACTOR.
|
INSP - Final | 2/20/1997 | 2/20/1997 | 2/21/1997 | P | PART |
|
|
|
visual alarms in handicap rooms ok, reviewed emergency generator problems with contractor
|
INSP - Final | 2/18/1997 | 2/20/1997 | 2/20/1997 | A | PASS |
Jim Storey
|
|
|
02/20/97 301 - FNL -OK FINAL for temp occ. OTH-OTHER AGEN
|
INSP - Temporary occupancy | 2/19/1997 | 2/19/1997 | 2/19/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - TCO -TEMP C OF O ISSUED
|
INSP - Final | 2/11/1997 | 2/11/1997 | 2/11/1997 | P | PART |
|
|
|
TESTED GENERATOR, ISSUED C/N FOR PERMANENT OCCUPANCY, SIGNED TEMP OCC
|
INSP - Final | 2/7/1997 | 2/11/1997 | 2/11/1997 | A | PART |
Jim Storey
|
|
|
02/11/97 301 - FINAL FOR C/O. CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Final | 2/10/1997 | 2/10/1997 | 2/10/1997 | A | NR |
|
|
|
reinspection...SPRINKLERS AND GENERATOR STILL NOT READY
|
INSP - Final | 2/10/1997 | 2/10/1997 | 2/10/1997 | P | PART |
|
|
|
TO TEST COOKING HOOD, GENERATOR, AND SPRINKLERS HOOD OK, SPRINKLERS OK, GENERATOR NOT READY
|
INSP - Final | 2/5/1997 | 2/7/1997 | 2/7/1997 | A | FAIL |
|
|
|
830 am alarms and sprinkler flow test SPRINKLERS STILL NOT WORKING, LONG C/N PUNCH LIST CREATED FOR GENERAL, SHOOTING FOR MONDAY
|
INSP - Final | 2/5/1997 | 2/5/1997 | 2/5/1997 | A | NR |
|
|
|
alarm testing at 9 am alarms not ready, sprinklers not ready, rescheduled for fri am.
|
INSP-Supply line flush | 2/5/1997 | 2/5/1997 | 2/5/1997 | A | PASS |
|
|
|
need to verify piv does close piv functions after line flushed......lots of dirt and rocks
|
INSP-Sprinkler Rough-in/Hydro | 2/5/1997 | 2/4/1997 | 2/4/1997 | P | PART |
|
|
|
ug hydro tested, not flushed, piv wont close
|
INSP-Sprinkler Rough-in/Hydro | 1/28/1997 | 1/30/1997 | 1/30/1997 | P | PART |
Joe Tawney
|
|
|
MIKE - ###-#### OK ON HYDRO TESTS FOR WET & DRY SYSTEMS
|
INSP - Energy code compliance | 1/15/1997 | 1/15/1997 | 1/15/1997 | P | PASS |
Jim Storey
|
|
|
01/15/97 301 -
|
INSP - Wall cover | 1/15/1997 | 1/15/1997 | 1/15/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - shaft for kitchen hood ok
|
INSP - Energy code compliance | 12/17/1996 | 12/20/1996 | 12/23/1996 | A | PASS |
Jim Storey
|
|
|
12/23/96 301 - INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 12/17/1996 | 12/19/1996 | 12/19/1996 | A | PASS |
Jim Storey
|
|
|
12/19/96 301 - FRAM-OK FRAMING a-3 occ area
|
INSP - Energy code compliance | 12/17/1996 | 12/17/1996 | 12/17/1996 | P | PASS |
Jim Storey
|
|
|
12/17/96 301 - INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 12/13/1996 | 12/17/1996 | 12/17/1996 | P | PASS |
Jim Storey
|
|
|
12/17/96 301 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 12/13/1996 | 12/13/1996 | 12/13/1996 | P | NR |
Jim Storey
|
|
|
12/13/96 301 - OTH-OTHER AGENCIES NOT APPROVED ele. n/r for framing.
|
INSP - Framing/Rough-in | 12/11/1996 | 12/12/1996 | 12/12/1996 | P | PASS |
Jim Storey
|
|
|
12/12/96 301 - PRE-INSULATION IN ATTIC GWB -OK SHEETROCK NAILING
|
INSP - Energy code compliance | 12/6/1996 | 12/9/1996 | 12/9/1996 | A | PASS |
Jim Storey
|
|
|
12/09/96 301 - EARY MONDAY A.M. INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 12/6/1996 | 12/9/1996 | 12/9/1996 | A | PASS |
Jim Storey
|
|
|
12/09/96 301 - EARLY A.M. FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 12/5/1996 | 12/5/1996 | 12/5/1996 | P | FAIL |
Jim Storey
|
|
|
12/05/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Energy code compliance | 12/2/1996 | 12/3/1996 | 12/3/1996 | A | PASS |
Jim Storey
|
|
|
12/03/96 301 - EARLY A.M. INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 11/26/1996 | 12/3/1996 | 12/3/1996 | P | PASS |
Jim Storey
|
|
|
12/03/96 301 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 11/26/1996 | 11/27/1996 | 11/27/1996 | P | PART |
Jim Storey
|
|
|
11/27/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok to insulate.
|
INSP - Framing/Rough-in | 11/22/1996 | 11/26/1996 | 11/26/1996 | P | CANC |
Jim Storey
|
|
|
11/25/96 301 - contractor cancled
|
INSP - Conference | 11/19/1996 | 11/19/1996 | 11/19/1996 | | PASS |
|
|
|
/ / 405 - reviewed alarm plans with installer
|
INSP - Fire Dept. Request | 11/19/1996 | 11/19/1996 | 11/19/1996 | | PASS |
|
|
|
/ / 405 - middle wing, 2nd floor ok to cover...c/n isues resolved
|
INSP - Framing/Rough-in | 11/18/1996 | 11/19/1996 | 11/19/1996 | A | PART |
Jim Storey
|
|
|
11/19/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Fire Dept. Request | 11/15/1996 | 11/15/1996 | 11/15/1996 | | FAIL |
|
|
|
/ / 405 - rough-in middle wing, 2nd floor, failed...c/n issued support spacing excessive where crossing copper water lines
|
INSP-Conference | 11/13/1996 | 11/13/1996 | 11/13/1996 | | PASS |
|
|
|
DISCUSSED ELEVATOR SHAFT SPRINKLER REQUIREMENTS, GAVE CONTRACTOR LETTER IN WRITING
|
INSP - Final | 11/8/1996 | 11/12/1996 | 11/12/1996 | A | NR |
Jim Storey
|
|
|
11/12/96 301 -
|
INSP - Framing/Rough-in | 11/12/1996 | 11/12/1996 | 11/12/1996 | P | PASS |
Jim Storey
|
|
|
11/12/96 301 - FRAM-OK FRAMING INSL-OK INSULATION-ENERGY CODE south wing first floor only.
|
INSP-Sprinkler Rough-in/Hydro | 11/7/1996 | 11/7/1996 | 11/7/1996 | | PART |
|
|
|
NORTH WING ATTIC AND 2ND FLOOR APPROVED FOR COVER
|
INSP - Framing/Rough-in | 11/1/1996 | 11/4/1996 | 11/4/1996 | P | FAIL |
Jim Storey
|
|
|
11/04/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 11/4/1996 | 11/4/1996 | 11/4/1996 | | FAIL |
Jim Storey
|
|
|
10/31/96 301 - EARLY AS POSSIBLE PLEASE CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Wall cover | 10/17/1996 | 10/17/1996 | 10/17/1996 | P | PASS |
Jim Storey
|
|
|
10/17/96 301 - EXTERIOR SHEER WALL NAILLING OK FRONT OF BLDG.
|
INSP - Conference | 8/29/1996 | 8/29/1996 | 8/29/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - pre-const meeting w/arch, owner,genral and subcontractors.
|
INSP - Conference | 8/29/1996 | 8/29/1996 | 8/29/1996 | | PASS |
|
|
|
/ / 405 - precon meeting
|
INSP - Conference | 8/26/1996 | 8/26/1996 | 8/26/1996 | | PART |
|
|
|
/ / 405 - chk FD access to site, radius, etc entrance only 15 ft wide from park center, numbering needs to be discuss to how to mark buildings. hydrants somewhat diffewrent than plans ...as builts should be prov
|
INSP - Footings | 7/19/1996 | 7/22/1996 | 7/19/1996 | A | CANC |
Jim Sly
|
|
|
07/19/96 316 - Cancel...sent to...
|