INSP - Final | 7/16/1998 | 7/16/1998 | 7/16/1998 | A | PASS |
|
|
|
07/16/98 333 - FNL -OK FINAL
|
Permanent Occupancy | | 7/15/1998 | 7/15/1998 | | DONE |
|
|
|
|
Permanent Occupancy | | 7/15/1998 | 7/15/1998 | | DONE |
|
|
|
|
INSP - Final | 7/14/1998 | 7/14/1998 | 7/14/1998 | | PART |
|
|
|
/ / 333 - PROFIT MEETING
|
INSP - Final | 6/29/1998 | 6/29/1998 | 6/29/1998 | | PART |
|
|
|
/ / 333 - TALKED TO ROGER ABOUT FINAL REQUIREMENTS
|
INSP - Final | 6/16/1998 | 6/16/1998 | 6/16/1998 | | FAIL |
|
|
|
/ / 333 - CN PLACED TEMP EXPIRED
|
INSP - Final | 6/11/1998 | 6/11/1998 | 6/11/1998 | A | FAIL |
|
|
|
06/11/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Alarm Testing | 5/12/1998 | 5/12/1998 | 5/12/1998 | P | PART |
Rick Jackson
|
|
|
tested alarms and door holders for 14th floor shell - okay. need to recheck penetrations by stair 3.
|
INSP-Final Inspection | 5/11/1998 | 5/11/1998 | 5/11/1998 | P | PART |
Rick Jackson
|
|
|
14th floor core and shell temp occ approved. corridor near stair 3 not complete. escutcheons for 2 sprinklers near stair 2. strobe not within 15 feet near stair 3.
|
INSP - Final | 3/26/1998 | 3/26/1998 | 3/26/1998 | | PART |
|
|
|
/ / 333 - profit meeting
|
INSP - Framing/Rough-in | 3/16/1998 | 3/16/1998 | 3/16/1998 | A | PART |
|
|
|
03/16/98 333 - talked with Skip about resub on corridor doors
|
INSP-Final Inspection | 3/11/1998 | 3/11/1998 | 3/11/1998 | P | FAIL |
|
|
|
dave ###-#### 3rd floor not ready - walked through....need to add strobe to view suite
|
INSP - Framing/Rough-in | 3/3/1998 | 3/4/1998 | 3/4/1998 | | NR |
|
|
|
03/04/98 333 - wrong permit # 15th floor at 2:00, if possible - see the ofc.
|
INSP - Conference | 2/5/1998 | 2/5/1998 | 2/5/1998 | | PASS |
|
|
|
/ / 333 - resubmittal of sprink at 3rd floor suites
|
INSP - Conference | 1/22/1998 | 1/22/1998 | 1/22/1998 | | PART |
|
|
|
/ / 333 - discussed damper issues and shafts with roger
|
INSP - Final | 1/21/1998 | 1/21/1998 | 1/21/1998 | P | PART |
|
|
|
01/21/98 333 - 11 and 12 ok for temp
|
INSP - Framing/Rough-in | 1/21/1998 | 1/21/1998 | 1/21/1998 | A | PASS |
|
|
|
01/21/98 333 - 13 ok
|
INSP - Final | 1/20/1998 | 1/20/1998 | 1/20/1998 | | FAIL |
|
|
|
/ / 333 - 12th floor not ready
|
INSP - Final | 1/16/1998 | 1/16/1998 | 1/16/1998 | P | FAIL |
|
|
|
11 not ready
|
INSP - Final | 1/14/1998 | 1/14/1998 | 1/14/1998 | | PART |
|
|
|
/ / 333 - elevator tests
|
INSP - Conference | 1/12/1998 | 1/12/1998 | 1/12/1998 | | PASS |
Tom Arcoraci
|
|
|
/ / 408 -
|
INSP - Conference | 1/12/1998 | 1/12/1998 | 1/12/1998 | | PASS |
Tom Arcoraci
|
|
|
/ / 408 -
|
INSP - Final | 1/12/1998 | 1/12/1998 | 1/12/1998 | | PART |
|
|
|
/ / 333 -
|
INSP - Framing/Rough-in | 1/9/1998 | 1/9/1998 | 1/8/1998 | P | PASS |
|
|
|
01/09/98 333 - 13th floor framing ok
|
INSP - Ceiling grid | 1/8/1998 | 1/8/1998 | 1/8/1998 | | PART |
|
|
|
/ / 333 -
|
INSP - Conference | 1/5/1998 | 1/5/1998 | 1/5/1998 | | PART |
|
|
|
/ / 333 -
|
INSP - Final | 12/31/1997 | 12/31/1997 | 12/31/1997 | A | PART |
|
|
|
12/31/97 333 - all up to 10 ok for temp
|
INSP - Final | 12/30/1997 | 12/30/1997 | 12/30/1997 | P | FAIL |
|
|
|
12/30/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 12/29/1997 | 12/29/1997 | 12/29/1997 | P | FAIL |
|
|
|
12/29/97 333 - cn not made
|
INSP - Final | 12/23/1997 | 12/23/1997 | 12/23/1997 | | PART |
|
|
|
/ / 333 -
|
INSP - Wall cover | 12/19/1997 | 12/19/1997 | 12/19/1997 | | PART |
|
|
|
/ / 333 -
|
INSP - Conference | 12/18/1997 | 12/18/1997 | 12/18/1997 | | PASS |
|
|
|
/ / 333 -
|
INSP - Conference | 12/15/1997 | 12/15/1997 | 12/15/1997 | P | PASS |
|
|
|
12/15/97 333 - talked about stair pressurization with Jackie
|
INSP - Conference | 12/12/1997 | 12/12/1997 | 12/12/1997 | | PASS |
|
|
|
/ / 333 -
|
INSP - Conference | 12/11/1997 | 12/11/1997 | 12/11/1997 | | PASS |
|
|
|
/ / 333 -
|
INSP - Framing/Rough-in | 12/9/1997 | 12/9/1997 | 12/9/1997 | | PART |
|
|
|
/ / 333 - 12th ceiling
|
INSP - Framing/Rough-in | 12/8/1997 | 12/8/1997 | 12/8/1997 | P | PART |
|
|
|
12/08/97 333 - 12th ok
|
INSP - Framing/Rough-in | 12/4/1997 | 12/4/1997 | 12/4/1997 | A | PART |
|
|
|
12/04/97 333 - ceilings ok
|
INSP - Framing/Rough-in | 12/3/1997 | 12/3/1997 | 12/3/1997 | | PASS |
|
|
|
/ / 333 - ceilings on 12 ok
|
INSP - Conference | 12/2/1997 | 12/2/1997 | 12/2/1997 | | PASS |
|
|
|
/ / 333 -
|
INSP - Framing/Rough-in | 11/28/1997 | 11/28/1997 | 11/28/1997 | | PART |
|
|
|
/ / 333 - 12TH CORRIDORS OK
|
INSP - Framing/Rough-in | 11/26/1997 | 11/26/1997 | 11/26/1997 | P | FAIL |
|
|
|
11/26/97 333 - cn not made 12th
|
INSP - Framing/Rough-in | 11/25/1997 | 11/25/1997 | 11/25/1997 | A | FAIL |
|
|
|
11/25/97 333 - cn 12th floor
|
INSP - Conference | 11/20/1997 | 11/20/1997 | 11/20/1997 | | PASS |
|
|
|
/ / 333 - firestoping 10
|
INSP - Framing/Rough-in | 11/19/1997 | 11/19/1997 | 11/19/1997 | A | PART |
|
|
|
11/19/97 333 - 8 ande 9 ok
|
INSP - Framing/Rough-in | 11/18/1997 | 11/18/1997 | 11/18/1997 | P | FAIL |
|
|
|
11/18/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED 9&10
|
INSP - Framing/Rough-in | 11/13/1997 | 11/13/1997 | 11/13/1997 | A | PART |
|
|
|
11/13/97 333 - 11th ok
|
INSP - Framing/Rough-in | 11/7/1997 | 11/7/1997 | 11/7/1997 | | PASS |
|
|
|
/ / 333 - 10 ok
|
INSP - Framing/Rough-in | 11/6/1997 | 11/6/1997 | 11/6/1997 | | FAIL |
|
|
|
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED 9th floor
|
INSP - Framing/Rough-in | 11/3/1997 | 11/3/1997 | 11/3/1997 | A | PART |
|
|
|
11/03/97 333 - 4th floor part
|
INSP - Framing/Rough-in | 10/31/1997 | 10/31/1997 | 10/31/1997 | A | PART |
|
|
|
10/31/97 333 - 7th floor all but corridir and end units
|
INSP - Framing/Rough-in | 10/30/1997 | 10/30/1997 | 10/30/1997 | A | PART |
|
|
|
10/30/97 333 - 7th in progress
|
INSP - Framing/Rough-in | 10/29/1997 | 10/29/1997 | 10/29/1997 | | PART |
|
|
|
/ / 333 - discussed dampers for shafe next to main elevator
|
INSP - Framing/Rough-in | 10/28/1997 | 10/28/1997 | 10/28/1997 | | PART |
|
|
|
/ / 333 - 8th floor corridor ok
|
INSP - Framing/Rough-in | 10/28/1997 | 10/28/1997 | 10/28/1997 | | PASS |
|
|
|
/ / 333 - 6th floor corridor ok
|
INSP - Framing/Rough-in | 10/27/1997 | 10/27/1997 | 10/27/1997 | P | PART |
|
|
|
8th floor all but corridor and north and south units
|
INSP - Stop Work Order | 10/24/1997 | 10/24/1997 | 10/24/1997 | | FAIL |
|
|
|
/ / 333 - glazing at grove patio without permit
|
INSP - Framing/Rough-in | 10/23/1997 | 10/23/1997 | 10/23/1997 | A | PART |
|
|
|
10/23/97 333 - 8th all but corridor and shafts
|
INSP - Stop Work Order | 10/22/1997 | 10/22/1997 | 10/22/1997 | | FAIL |
|
|
|
/ / 333 - glazing at grove no permit
|
INSP-Conference | 10/22/1997 | 10/22/1997 | 10/22/1997 | P | PART |
|
|
|
meeting w/ pcl and sassco on outstanding issues, list given to all, copy to S hyde of Block 22
|
INSP - Framing/Rough-in | 10/21/1997 | 10/21/1997 | 10/21/1997 | | PART |
|
|
|
/ / 333 - 7th corridor
|
INSP - Framing/Rough-in | 10/20/1997 | 10/20/1997 | 10/20/1997 | | FAIL |
|
|
|
/ / 333 - 7th floor CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Wall cover | 10/14/1997 | 10/14/1997 | 10/14/1997 | A | PART |
|
|
|
10/14/97 333 - ok to cover 6th corridors
|
INSP - Framing/Rough-in | 10/13/1997 | 10/13/1997 | 10/13/1997 | A | FAIL |
|
|
|
10/13/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL
|
INSP - Wall cover | 10/10/1997 | 10/10/1997 | 10/10/1997 | P | FAIL |
|
|
|
10/10/97 333 - 6th floor not ready
|
INSP - Framing/Rough-in | 10/9/1997 | 10/9/1997 | 10/9/1997 | P | FAIL |
|
|
|
10/09/97 333 - 6th not ready
|
INSP - Framing/Rough-in | 10/8/1997 | 10/8/1997 | 10/8/1997 | | FAIL |
|
|
|
10/08/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL 6TH FLOOR
|
INSP - Framing/Rough-in | 10/6/1997 | 10/6/1997 | 10/6/1997 | A | PART |
|
|
|
10/06/97 333 - corridor to not cover
|
INSP - Wall cover | 10/3/1997 | 10/3/1997 | 10/3/1997 | A | PART |
|
|
|
10/03/97 333 - ceilings at event level kit ok
|
INSP - Framing/Rough-in | 10/1/1997 | 10/1/1997 | 10/1/1997 | P | FAIL |
|
|
|
cn
|
INSP - Wall cover | 9/30/1997 | 9/30/1997 | 9/30/1997 | A | PASS |
|
|
|
09/30/97 333 - bathrooms ok
|
INSP - Framing/Rough-in | 9/29/1997 | 9/29/1997 | 9/29/1997 | | PART |
|
|
|
/ / 333 - part
|
INSP - Framing/Rough-in | 9/26/1997 | 9/26/1997 | 9/26/1997 | A | PART |
|
|
|
09/26/97 333 - cn placed
|
INSP - Framing/Rough-in | 9/22/1997 | 9/22/1997 | 9/22/1997 | | PART |
|
|
|
/ / 333 - part
|
INSP - Framing/Rough-in | 9/12/1997 | 9/12/1997 | 9/12/1997 | A | PART |
|
|
|
stairs
|
INSP - Framing/Rough-in | 9/9/1997 | 9/9/1997 | 9/9/1997 | A | PART |
|
|
|
09/09/97 333 - 2nd floor corridor lid
|
INSP - Framing/Rough-in | 9/8/1997 | 9/8/1997 | 9/8/1997 | A | FAIL |
|
|
|
09/08/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 9/8/1997 | 9/8/1997 | 9/8/1997 | P | FAIL |
|
|
|
09/08/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Wall cover | 9/5/1997 | 9/5/1997 | 9/5/1997 | A | PART |
|
|
|
first floor arena level cn
|
INSP-Conference | 9/4/1997 | 9/5/1997 | 9/4/1997 | P | |
|
|
|
2:30
|
INSP - Wall cover | 9/4/1997 | 9/4/1997 | 9/4/1997 | A | FAIL |
|
|
|
09/04/97 333 - 2nd floor lids not corrected
|
INSP-Sprinkler Rough-in/Hydro | 9/3/1997 | 9/4/1997 | 9/4/1997 | P | PART |
|
|
|
fire pump acceptance test 1pm to 4pm fire pump and controller passed, no alarm connection
|
INSP - Framing/Rough-in | 9/3/1997 | 9/3/1997 | 9/3/1997 | | FAIL |
|
|
|
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Sprinkler Rough-in/Hydro | 9/3/1997 | 9/3/1997 | 9/3/1997 | P | FAIL |
|
|
|
refer pressure at 1:30, not ready at 3:30 event rough in complete, 3/4 of level capped or incorrect informed j trach that fuel tank installer was not running emergency vent outside
|
INSP - Carpentry | 9/2/1997 | 9/2/1997 | 9/2/1997 | | PASS |
|
|
|
/ / 333 - GEN -GENERAL INSPECTION
|
INSP-Sprinkler Rough-in/Hydro | 9/2/1997 | 9/2/1997 | 9/2/1997 | P | FAIL |
|
|
|
HYDRO REFER PIPING NOT READY, LEAKS ROUGH-IN, EVEENT LEVEL....MOST NOT COMPLETE, MAKING LIST
|
INSP - Conference | 8/29/1997 | 8/29/1997 | 8/29/1997 | | PASS |
|
|
|
/ / 333 - met with John C
|
INSP - Carpentry | 8/28/1997 | 8/28/1997 | 8/28/1997 | A | PASS |
|
|
|
08/28/97 333 - meeting about elect
|
INSP - Conference | 8/27/1997 | 8/27/1997 | 8/27/1997 | | PASS |
|
|
|
/ / 333 - met with powers
|
INSP - Carpentry | 8/26/1997 | 8/26/1997 | 8/26/1997 | | PASS |
|
|
|
/ / 333 - talked to Jackie about inspections
|
INSP - Conference | 8/25/1997 | 8/25/1997 | 8/25/1997 | | PASS |
|
|
|
/ / 333 - met with rich and jackie
|
INSP - Conference | 8/21/1997 | 8/21/1997 | 8/21/1997 | A | PASS |
|
|
|
08/21/97 333 - met with arch and pcl floyd george other inspectors
|
INSP - Conference | 8/21/1997 | 8/21/1997 | 8/21/1997 | | PASS |
|
|
|
/ / 333 - met with john
|
INSP-Conference | 8/20/1997 | 8/21/1997 | 8/21/1997 | A | PART |
|
|
|
ice making to be with r22, no h occupancy, fuel tanks to be in h3's, questions in providing ventilation per code, want exception to sprinkling floors 6 through 13. will arrainge meeting.
|
INSP - Conference | 8/21/1997 | 8/20/1997 | 8/20/1997 | P | PASS |
|
|
|
accepted reqsuest on pool piping
|
INSP - Framing/Rough-in | 8/18/1997 | 8/18/1997 | 8/18/1997 | | FAIL |
|
|
|
08/18/97 333 - cn on visqueen and plumbing penetrations
|
INSP-Conference | 8/18/1997 | 8/18/1997 | 8/18/1997 | A | PART |
|
|
|
conference with skip hyde re rated tank substitution for control area. discussed use as liquid storage room, requirements for equivalence to code intent
|
INSP - Framing/Rough-in | 8/15/1997 | 8/15/1997 | 8/15/1997 | | PART |
|
|
|
08/15/97 333 - ok to cover 3rd floor corridor
|
INSP-Conference | 8/15/1997 | 8/15/1997 | 8/15/1997 | P | PART |
|
|
|
MEETING WITH jACKIE OF pcl ON NEW STORAGE TANK IDEA. DISCUSSED LOCATIONS AND SUBMITTAL FORM. PCL TO PREPARE PROPOSAL FOR CONSIDERATION OF THE TANK AS A ALTERNATIVE TO LIQUID STORAGE ROOM ADDRESSING EACH CODE REQUIREMENT IN 91 UFC AND HOW THEIR DESIGN IS EQUIVALENT
|
INSP - Framing/Rough-in | 8/14/1997 | 8/13/1997 | 8/13/1997 | P | FAIL |
|
|
|
checked cn on 3rd floor
|
INSP - Conference | 8/12/1997 | 8/12/1997 | 8/12/1997 | | PASS |
|
|
|
/ / 333 - met with John talked about firestoping at sinks and 2nd and
|
INSP-Conference | 8/12/1997 | 8/12/1997 | 8/12/1997 | P | PART |
|
|
|
meeting on site w/ hyde of block 22 and joyce of HNTB amd pcl reps. discussed fuel storage options, will reply in writing on fire pump fuel capacity requirements and proposals
|
INSP - Resubmittals | 8/8/1997 | 8/8/1997 | 8/8/1997 | P | PASS |
|
|
|
08/08/97 333 - recieved plan for temp
|
INSP - Carpentry | 8/7/1997 | 8/7/1997 | 8/7/1997 | | PASS |
|
|
|
/ / 333 - talked to John about PVC pipe
|
INSP - Carpentry | 8/6/1997 | 8/6/1997 | 8/6/1997 | | PASS |
|
|
|
/ / 333 - asked Marlene for all transmittals from Seattle about all is
|
INSP - Carpentry | 8/5/1997 | 8/5/1997 | 8/5/1997 | | PASS |
|
|
|
/ / 333 - met with archetect and pcl about fire issues
|
INSP - Carpentry | 8/4/1997 | 8/4/1997 | 8/4/1997 | A | PASS |
|
|
|
reviewed firestoping requirements
|
INSP - Wall cover | 8/1/1997 | 8/1/1997 | 8/1/1997 | A | FAIL |
|
|
|
08/01/97 333 - talked with John Cunningham about refer room and desel st
|
INSP - Carpentry | 7/31/1997 | 7/31/1997 | 7/31/1997 | | FAIL |
|
|
|
/ / 333 - met with subs about anular space at firestops and slopy job
|
INSP - Carpentry | 7/31/1997 | 7/31/1997 | 7/31/1997 | | FAIL |
|
|
|
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Wall cover | 7/28/1997 | 7/28/1997 | 7/28/1997 | | PASS |
|
|
|
/ / 333 - 3rd floor in progress
|
INSP - Conference | 7/25/1997 | 7/25/1997 | 7/25/1997 | A | PASS |
|
|
|
/ / 333 - in progress
|
INSP - Conference | 7/23/1997 | 7/23/1997 | 7/23/1997 | P | PASS |
|
|
|
07/23/97 333 - review shaft requirements at pizza hut
|
INSP - Carpentry | 7/23/1997 | 7/22/1997 | 7/23/1997 | P | PASS |
|
|
|
/ / 333 - met with Rich
|
INSP - Carpentry | 7/21/1997 | 7/21/1997 | 7/21/1997 | A | PART |
|
|
|
07/21/97 333 - pool resubmittal to Carl W
|
INSP - Framing/Rough-in | 7/21/1997 | 7/21/1997 | 7/21/1997 | A | PART |
|
|
|
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED 3rd floor
|
INSP - Framing/Rough-in | 7/18/1997 | 7/18/1997 | 7/18/1997 | A | PART |
|
|
|
/ / 333 - 3rd floor partial
|
INSP-Sprinkler Rough-in/Hydro | 7/17/1997 | 7/17/1997 | 7/17/1997 | A | FAIL |
Joe Tawney
|
|
|
walkthrough of floors 1-6 and penthouse for sprinkler locations and bracing. plans not available, bracing not complete, some obstructions noted, all areas not covered, porte coutre not covered
|
INSP - Carpentry | 7/11/1997 | 7/11/1997 | 7/11/1997 | | PART |
|
|
|
07/14/97 333 - reviewed floor sinks and firestoping in arena
|
INSP - Carpentry | 7/10/1997 | 7/10/1997 | 7/10/1997 | | PASS |
|
|
|
07/09/97 333 - second floor in progress of cover
|
INSP-Sprinkler Rough-in/Hydro | 7/7/1997 | 7/8/1997 | 7/8/1997 | A | PASS |
Joe Tawney
|
|
|
07/08/97 406 - PLEASE GO OUT AT 10:00 UNITED WATER IS SCHEDULED AT THE S OK ON UNDERGROUND FLUSH
|
INSP - Carpentry | 7/6/1997 | 7/6/1997 | 7/6/1997 | | PASS |
|
|
|
07/06/97 333 - reviewed site
|
INSP - Carpentry | 7/2/1997 | 7/2/1997 | 7/2/1997 | | PASS |
|
|
|
/ / 333 - met with Jackie about shaft details gave resubmittal for 4th floor to plan review
|
INSP - Wall cover | 7/1/1997 | 7/1/1997 | 7/1/1997 | A | PART |
|
|
|
07/01/97 333 - second floor partial
|
INSP - Conference | 6/30/1997 | 6/27/1997 | 6/27/1997 | P | PASS |
|
|
|
second floor
|
INSP - Conference | 6/27/1997 | 6/26/1997 | 6/26/1997 | P | PASS |
|
|
|
met with Rich
|
INSP - Framing/Rough-in | 6/19/1997 | 6/19/1997 | 6/19/1997 | | FAIL |
|
|
|
06/18/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL
|
INSP - Framing/Rough-in | 6/19/1997 | 6/19/1997 | 6/19/1997 | | FAIL |
|
|
|
06/18/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL
|
INSP - Conference | 6/18/1997 | 6/17/1997 | 6/17/1997 | P | PASS |
|
|
|
met with architect and owners about requirements for temp for arena only
|
INSP - Conference | 6/16/1997 | 6/16/1997 | 6/16/1997 | | PASS |
|
|
|
06/15/97 333 - 2nd floor dampers ok
|
INSP - Framing/Rough-in | 6/11/1997 | 6/11/1997 | 6/11/1997 | | PART |
|
|
|
/ / 333 - 2nd floor framing ok to cover all but shafts dampers not in need to look at floor closure at stair/elevator shaft
|
INSP - Conference | 6/10/1997 | 6/10/1997 | 6/9/1997 | P | PASS |
|
|
|
06/10/97 333 - sent letter To John C
|
INSP - Framing/Rough-in | 6/9/1997 | 6/9/1997 | 6/9/1997 | P | FAIL |
|
|
|
dampers not in
|
INSP - Framing/Rough-in | 6/4/1997 | 6/4/1997 | 6/4/1997 | | FAIL |
|
|
|
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 6/4/1997 | 6/4/1997 | 6/4/1997 | | FAIL |
|
|
|
06/04/97 333 - CN PLACED
|
INSP - Carpentry | 5/21/1997 | 5/21/1997 | 5/21/1997 | | PASS |
|
|
|
/ / 333 - met with Rich left letter for John
|
INSP - Conference | 5/11/1997 | 5/11/1997 | 5/11/1997 | | PASS |
|
|
|
/ / 333 - met with John Cunningham
|
INSP - Conference | 5/11/1997 | 5/11/1997 | 5/11/1997 | | PASS |
|
|
|
/ / 333 - met with Rich
|
INSP - Conference | 5/11/1997 | 5/11/1997 | 5/11/1997 | | PASS |
|
|
|
/ / 333 - reviewed submittal
|
INSP - Conference | 5/7/1997 | 5/7/1997 | 5/7/1997 | | PASS |
|
|
|
/ / 333 - worked on letter about dampers talked with ISI about 1 hr exterior walls
|
INSP - Conference | 5/7/1997 | 5/7/1997 | 5/6/1997 | P | PASS |
|
|
|
05/07/97 333 - met with all subs about firestoping
|
INSP - Conference | 5/4/1997 | 5/4/1997 | 5/4/1997 | | PASS |
|
|
|
/ / 333 - reviewed firestoping with Bob
|
INSP - Conference | 4/30/1997 | 4/30/1997 | 4/30/1997 | | PASS |
|
|
|
/ / 333 - sent letter of transmittal to John
|
INSP - Conference | 4/28/1997 | 4/28/1997 | 4/28/1997 | | PASS |
|
|
|
/ / 333 - sent Letter Of Transmittal to John Cunningham
|
INSP - Conference | 4/27/1997 | 4/27/1997 | 4/27/1997 | | PASS |
|
|
|
/ / 333 - approved firestop method at efis panels at floor
|
INSP - Conference | 4/24/1997 | 4/24/1997 | 4/24/1997 | | PASS |
|
|
|
/ / 333 - sent letter of transmittal about firestop at floor lines
|
INSP - Conference | 4/20/1997 | 4/20/1997 | 4/20/1997 | | PASS |
|
|
|
/ / 333 - reviewed details with rich
|
INSP - Carpentry | 4/16/1997 | 4/16/1997 | 4/16/1997 | | PASS |
|
|
|
/ / 333 - in progress
|
INSP - Conference | 4/13/1997 | 4/13/1997 | 4/13/1997 | | PASS |
|
|
|
/ / 333 - MET WITH RICH FIRESTOPING AT WALL TO BEAM ATTACHMENT EXTERIOR WALLS OK
|
INSP - Conference | 4/7/1997 | 4/7/1997 | 4/6/1997 | A | PASS |
|
|
|
04/07/97 333 - talked to mti met with rich
|
INSP - Carpentry | 3/26/1997 | 3/26/1997 | 3/26/1997 | | PASS |
|
|
|
/ / 333 - framing in progress asked elect plumbing and mech for firestopping submittals
|
INSP - Carpentry | 3/24/1997 | 3/24/1997 | 3/24/1997 | | PASS |
|
|
|
/ / 333 - talked about wood cap at parapet
|
INSP - Conference | 3/24/1997 | 3/24/1997 | 3/23/1997 | P | PASS |
|
|
|
03/24/97 333 - talked to elect , plumb , and mech about submittals for f looked at framing west and south walls need detail for top connection 1hr wall as asked for in transmittal of last week
|
INSP - Conference | 3/20/1997 | 3/20/1997 | 3/20/1997 | A | PASS |
|
|
|
checked west and south fire wraps on beams
|
INSP - Conference | 3/7/1997 | 3/7/1997 | 3/6/1997 | P | PASS |
|
|
|
03/07/97 333 - sent letter of transmittal
|
INSP - Conference | 3/5/1997 | 3/6/1997 | 3/5/1997 | A | PASS |
|
|
|
03/06/97 333 - TALKED ABOUT FIREWALLS
|
INSP - Conference | 3/4/1997 | 3/5/1997 | 3/4/1997 | A | CANC |
|
|
|
03/05/97 333 - resent for thursday
|
INSP - Framing/Rough-in | 2/19/1997 | 2/19/1997 | 2/18/1997 | P | FAIL |
|
|
|
02/19/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|