Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberBLD96-00710
StatusFinaled
Name WESTCOAST HOTEL
Site Address 245 S CAPITOL BLVD
Project NameGROVE HOTEL
Customer Number 
ePlanReviewNo
Description
(WESTCOAST HOTEL & EVENTS CENTER)(SHELL AND CORE) TO COMPLETE THE SHELL AND CORE OF A 17 STORY HOTEL AND EVENTS CENTER. AREAS BEING COMPLETED ARE BASEMENT PARKING, STAIR ENCLOSURES, RESIDENTIAL STORAGE, ELEVATORS, ARENA AREA, SEATING LOCATIONS, OFFICE SPACES, TRAINING AREAS, EQUIPMENT ROOMS, CORRIDORS, LAUNDRY ROOMS, RESTROOMS, TRUCK DOCKS & RECEIVING, PRESS OFFICES, BROADCAST OFFICES, GENERATOR/HVAC PLATFORMS, EXECUTIVE SUITES, PREFUNCTION AREA, (3) BALLROOMS, VIEW SUITES, HOUSKEEPING ROOMS, BALLROOM MECHANICAL, 4TH FLOOR TERRACE, FLOORS 4TH & 5TH UNFINISHED, FLOORS 6TH THRU 13TH HOTEL SLEEPING ROOMS & CORRIDORS (NOTE! THESE FLOORS ARE COMPLETE), 14TH THRU 17TH FLOORS ARE UNFINISHED SPACES, THE PENTHOUSE IS COMPLETE, THE BALANCE OF THE BUILDING IS UNFINISHED AND WILL BE HANDLED AS TENANT IMPROVEMENTS. CONSTRUCTION TO BE ALL NONCOMBUSTIBLE MATERIALS INCLUDING PROTECTED STEEL, CONCRETE, PROTECTED STEEL STUDS WITH 5/8 TYPE X SHEET ROCK, SUSPENDED CEILINGS AND NONCOMBUSTIBLE FLOOR SYSTEMS. SEE ATTACHED PLAN REVIEW (PROJECT #153-96(BLD96-0710) DATED DECEMBER 4, 1996 FOR COMPLETE DESCRIPTION OF ALL APPROVED WORK AND SUBJECT TO FINAL APPROVAL FROM THE CCDC DESIGN COMMITTE FOR THE TREATMENT OF THE PEDESTAL STAIRWAY AT THE CORNER OF CAPITOL AND FRONT ALSO SUBJECT TO FINAL APPROVAL OF THE LANDSCAPE PLAN FOR THE PROJECT BY THE PLANNING DIVISION. ALL PER REVIEWED PLANS ON FILE. DR.#-23-95 CU.#-19-95 PC#-153-96.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final7/16/19987/16/19987/16/1998APASS
Details
07/16/98 333 - FNL -OK FINAL
Permanent Occupancy 7/15/19987/15/1998 DONE
Details
Permanent Occupancy 7/15/19987/15/1998 DONE
Details
INSP - Final7/14/19987/14/19987/14/1998 PART
Details
/ / 333 - PROFIT MEETING
INSP - Final6/29/19986/29/19986/29/1998 PART
Details
/ / 333 - TALKED TO ROGER ABOUT FINAL REQUIREMENTS
INSP - Final6/16/19986/16/19986/16/1998 FAIL
Details
/ / 333 - CN PLACED TEMP EXPIRED
INSP - Final6/11/19986/11/19986/11/1998AFAIL
Details
06/11/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP-Alarm Testing5/12/19985/12/19985/12/1998PPART
DetailsRick Jackson
tested alarms and door holders for 14th floor shell - okay. need to recheck penetrations by stair 3.
INSP-Final Inspection5/11/19985/11/19985/11/1998PPART
DetailsRick Jackson
14th floor core and shell temp occ approved. corridor near stair 3 not complete. escutcheons for 2 sprinklers near stair 2. strobe not within 15 feet near stair 3.
INSP - Final3/26/19983/26/19983/26/1998 PART
Details
/ / 333 - profit meeting
INSP - Framing/Rough-in3/16/19983/16/19983/16/1998APART
Details
03/16/98 333 - talked with Skip about resub on corridor doors
INSP-Final Inspection3/11/19983/11/19983/11/1998PFAIL
Details
dave ###-#### 3rd floor not ready - walked through....need to add strobe to view suite
INSP - Framing/Rough-in3/3/19983/4/19983/4/1998 NR
Details
03/04/98 333 - wrong permit # 15th floor at 2:00, if possible - see the ofc.
INSP - Conference2/5/19982/5/19982/5/1998 PASS
Details
/ / 333 - resubmittal of sprink at 3rd floor suites
INSP - Conference1/22/19981/22/19981/22/1998 PART
Details
/ / 333 - discussed damper issues and shafts with roger
INSP - Final1/21/19981/21/19981/21/1998PPART
Details
01/21/98 333 - 11 and 12 ok for temp
INSP - Framing/Rough-in1/21/19981/21/19981/21/1998APASS
Details
01/21/98 333 - 13 ok
INSP - Final1/20/19981/20/19981/20/1998 FAIL
Details
/ / 333 - 12th floor not ready
INSP - Final1/16/19981/16/19981/16/1998PFAIL
Details
11 not ready
INSP - Final1/14/19981/14/19981/14/1998 PART
Details
/ / 333 - elevator tests
INSP - Conference1/12/19981/12/19981/12/1998 PASS
DetailsTom Arcoraci
/ / 408 -
INSP - Conference1/12/19981/12/19981/12/1998 PASS
DetailsTom Arcoraci
/ / 408 -
INSP - Final1/12/19981/12/19981/12/1998 PART
Details
/ / 333 -
INSP - Framing/Rough-in1/9/19981/9/19981/8/1998PPASS
Details
01/09/98 333 - 13th floor framing ok
INSP - Ceiling grid1/8/19981/8/19981/8/1998 PART
Details
/ / 333 -
INSP - Conference1/5/19981/5/19981/5/1998 PART
Details
/ / 333 -
INSP - Final12/31/199712/31/199712/31/1997APART
Details
12/31/97 333 - all up to 10 ok for temp
INSP - Final12/30/199712/30/199712/30/1997PFAIL
Details
12/30/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Final12/29/199712/29/199712/29/1997PFAIL
Details
12/29/97 333 - cn not made
INSP - Final12/23/199712/23/199712/23/1997 PART
Details
/ / 333 -
INSP - Wall cover12/19/199712/19/199712/19/1997 PART
Details
/ / 333 -
INSP - Conference12/18/199712/18/199712/18/1997 PASS
Details
/ / 333 -
INSP - Conference12/15/199712/15/199712/15/1997PPASS
Details
12/15/97 333 - talked about stair pressurization with Jackie
INSP - Conference12/12/199712/12/199712/12/1997 PASS
Details
/ / 333 -
INSP - Conference12/11/199712/11/199712/11/1997 PASS
Details
/ / 333 -
INSP - Framing/Rough-in12/9/199712/9/199712/9/1997 PART
Details
/ / 333 - 12th ceiling
INSP - Framing/Rough-in12/8/199712/8/199712/8/1997PPART
Details
12/08/97 333 - 12th ok
INSP - Framing/Rough-in12/4/199712/4/199712/4/1997APART
Details
12/04/97 333 - ceilings ok
INSP - Framing/Rough-in12/3/199712/3/199712/3/1997 PASS
Details
/ / 333 - ceilings on 12 ok
INSP - Conference12/2/199712/2/199712/2/1997 PASS
Details
/ / 333 -
INSP - Framing/Rough-in11/28/199711/28/199711/28/1997 PART
Details
/ / 333 - 12TH CORRIDORS OK
INSP - Framing/Rough-in11/26/199711/26/199711/26/1997PFAIL
Details
11/26/97 333 - cn not made 12th
INSP - Framing/Rough-in11/25/199711/25/199711/25/1997AFAIL
Details
11/25/97 333 - cn 12th floor
INSP - Conference11/20/199711/20/199711/20/1997 PASS
Details
/ / 333 - firestoping 10
INSP - Framing/Rough-in11/19/199711/19/199711/19/1997APART
Details
11/19/97 333 - 8 ande 9 ok
INSP - Framing/Rough-in11/18/199711/18/199711/18/1997PFAIL
Details
11/18/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED 9&10
INSP - Framing/Rough-in11/13/199711/13/199711/13/1997APART
Details
11/13/97 333 - 11th ok
INSP - Framing/Rough-in11/7/199711/7/199711/7/1997 PASS
Details
/ / 333 - 10 ok
INSP - Framing/Rough-in11/6/199711/6/199711/6/1997 FAIL
Details
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED 9th floor
INSP - Framing/Rough-in11/3/199711/3/199711/3/1997APART
Details
11/03/97 333 - 4th floor part
INSP - Framing/Rough-in10/31/199710/31/199710/31/1997APART
Details
10/31/97 333 - 7th floor all but corridir and end units
INSP - Framing/Rough-in10/30/199710/30/199710/30/1997APART
Details
10/30/97 333 - 7th in progress
INSP - Framing/Rough-in10/29/199710/29/199710/29/1997 PART
Details
/ / 333 - discussed dampers for shafe next to main elevator
INSP - Framing/Rough-in10/28/199710/28/199710/28/1997 PART
Details
/ / 333 - 8th floor corridor ok
INSP - Framing/Rough-in10/28/199710/28/199710/28/1997 PASS
Details
/ / 333 - 6th floor corridor ok
INSP - Framing/Rough-in10/27/199710/27/199710/27/1997PPART
Details
8th floor all but corridor and north and south units
INSP - Stop Work Order10/24/199710/24/199710/24/1997 FAIL
Details
/ / 333 - glazing at grove patio without permit
INSP - Framing/Rough-in10/23/199710/23/199710/23/1997APART
Details
10/23/97 333 - 8th all but corridor and shafts
INSP - Stop Work Order10/22/199710/22/199710/22/1997 FAIL
Details
/ / 333 - glazing at grove no permit
INSP-Conference10/22/199710/22/199710/22/1997PPART
Details
meeting w/ pcl and sassco on outstanding issues, list given to all, copy to S hyde of Block 22
INSP - Framing/Rough-in10/21/199710/21/199710/21/1997 PART
Details
/ / 333 - 7th corridor
INSP - Framing/Rough-in10/20/199710/20/199710/20/1997 FAIL
Details
/ / 333 - 7th floor CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Wall cover10/14/199710/14/199710/14/1997APART
Details
10/14/97 333 - ok to cover 6th corridors
INSP - Framing/Rough-in10/13/199710/13/199710/13/1997AFAIL
Details
10/13/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL
INSP - Wall cover10/10/199710/10/199710/10/1997PFAIL
Details
10/10/97 333 - 6th floor not ready
INSP - Framing/Rough-in10/9/199710/9/199710/9/1997PFAIL
Details
10/09/97 333 - 6th not ready
INSP - Framing/Rough-in10/8/199710/8/199710/8/1997 FAIL
Details
10/08/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL 6TH FLOOR
INSP - Framing/Rough-in10/6/199710/6/199710/6/1997APART
Details
10/06/97 333 - corridor to not cover
INSP - Wall cover10/3/199710/3/199710/3/1997APART
Details
10/03/97 333 - ceilings at event level kit ok
INSP - Framing/Rough-in10/1/199710/1/199710/1/1997PFAIL
Details
cn
INSP - Wall cover9/30/19979/30/19979/30/1997APASS
Details
09/30/97 333 - bathrooms ok
INSP - Framing/Rough-in9/29/19979/29/19979/29/1997 PART
Details
/ / 333 - part
INSP - Framing/Rough-in9/26/19979/26/19979/26/1997APART
Details
09/26/97 333 - cn placed
INSP - Framing/Rough-in9/22/19979/22/19979/22/1997 PART
Details
/ / 333 - part
INSP - Framing/Rough-in9/12/19979/12/19979/12/1997APART
Details
stairs
INSP - Framing/Rough-in9/9/19979/9/19979/9/1997APART
Details
09/09/97 333 - 2nd floor corridor lid
INSP - Framing/Rough-in9/8/19979/8/19979/8/1997AFAIL
Details
09/08/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in9/8/19979/8/19979/8/1997PFAIL
Details
09/08/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Wall cover9/5/19979/5/19979/5/1997APART
Details
first floor arena level cn
INSP-Conference9/4/19979/5/19979/4/1997P
Details
2:30
INSP - Wall cover9/4/19979/4/19979/4/1997AFAIL
Details
09/04/97 333 - 2nd floor lids not corrected
INSP-Sprinkler Rough-in/Hydro9/3/19979/4/19979/4/1997PPART
Details
fire pump acceptance test 1pm to 4pm fire pump and controller passed, no alarm connection
INSP - Framing/Rough-in9/3/19979/3/19979/3/1997 FAIL
Details
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP-Sprinkler Rough-in/Hydro9/3/19979/3/19979/3/1997PFAIL
Details
refer pressure at 1:30, not ready at 3:30 event rough in complete, 3/4 of level capped or incorrect informed j trach that fuel tank installer was not running emergency vent outside
INSP - Carpentry9/2/19979/2/19979/2/1997 PASS
Details
/ / 333 - GEN -GENERAL INSPECTION
INSP-Sprinkler Rough-in/Hydro9/2/19979/2/19979/2/1997PFAIL
Details
HYDRO REFER PIPING NOT READY, LEAKS ROUGH-IN, EVEENT LEVEL....MOST NOT COMPLETE, MAKING LIST
INSP - Conference8/29/19978/29/19978/29/1997 PASS
Details
/ / 333 - met with John C
INSP - Carpentry8/28/19978/28/19978/28/1997APASS
Details
08/28/97 333 - meeting about elect
INSP - Conference8/27/19978/27/19978/27/1997 PASS
Details
/ / 333 - met with powers
INSP - Carpentry8/26/19978/26/19978/26/1997 PASS
Details
/ / 333 - talked to Jackie about inspections
INSP - Conference8/25/19978/25/19978/25/1997 PASS
Details
/ / 333 - met with rich and jackie
INSP - Conference8/21/19978/21/19978/21/1997APASS
Details
08/21/97 333 - met with arch and pcl floyd george other inspectors
INSP - Conference8/21/19978/21/19978/21/1997 PASS
Details
/ / 333 - met with john
INSP-Conference8/20/19978/21/19978/21/1997APART
Details
ice making to be with r22, no h occupancy, fuel tanks to be in h3's, questions in providing ventilation per code, want exception to sprinkling floors 6 through 13. will arrainge meeting.
INSP - Conference8/21/19978/20/19978/20/1997PPASS
Details
accepted reqsuest on pool piping
INSP - Framing/Rough-in8/18/19978/18/19978/18/1997 FAIL
Details
08/18/97 333 - cn on visqueen and plumbing penetrations
INSP-Conference8/18/19978/18/19978/18/1997APART
Details
conference with skip hyde re rated tank substitution for control area. discussed use as liquid storage room, requirements for equivalence to code intent
INSP - Framing/Rough-in8/15/19978/15/19978/15/1997 PART
Details
08/15/97 333 - ok to cover 3rd floor corridor
INSP-Conference8/15/19978/15/19978/15/1997PPART
Details
MEETING WITH jACKIE OF pcl ON NEW STORAGE TANK IDEA. DISCUSSED LOCATIONS AND SUBMITTAL FORM. PCL TO PREPARE PROPOSAL FOR CONSIDERATION OF THE TANK AS A ALTERNATIVE TO LIQUID STORAGE ROOM ADDRESSING EACH CODE REQUIREMENT IN 91 UFC AND HOW THEIR DESIGN IS EQUIVALENT
INSP - Framing/Rough-in8/14/19978/13/19978/13/1997PFAIL
Details
checked cn on 3rd floor
INSP - Conference8/12/19978/12/19978/12/1997 PASS
Details
/ / 333 - met with John talked about firestoping at sinks and 2nd and
INSP-Conference8/12/19978/12/19978/12/1997PPART
Details
meeting on site w/ hyde of block 22 and joyce of HNTB amd pcl reps. discussed fuel storage options, will reply in writing on fire pump fuel capacity requirements and proposals
INSP - Resubmittals8/8/19978/8/19978/8/1997PPASS
Details
08/08/97 333 - recieved plan for temp
INSP - Carpentry8/7/19978/7/19978/7/1997 PASS
Details
/ / 333 - talked to John about PVC pipe
INSP - Carpentry8/6/19978/6/19978/6/1997 PASS
Details
/ / 333 - asked Marlene for all transmittals from Seattle about all is
INSP - Carpentry8/5/19978/5/19978/5/1997 PASS
Details
/ / 333 - met with archetect and pcl about fire issues
INSP - Carpentry8/4/19978/4/19978/4/1997APASS
Details
reviewed firestoping requirements
INSP - Wall cover8/1/19978/1/19978/1/1997AFAIL
Details
08/01/97 333 - talked with John Cunningham about refer room and desel st
INSP - Carpentry7/31/19977/31/19977/31/1997 FAIL
Details
/ / 333 - met with subs about anular space at firestops and slopy job
INSP - Carpentry7/31/19977/31/19977/31/1997 FAIL
Details
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Wall cover7/28/19977/28/19977/28/1997 PASS
Details
/ / 333 - 3rd floor in progress
INSP - Conference7/25/19977/25/19977/25/1997APASS
Details
/ / 333 - in progress
INSP - Conference7/23/19977/23/19977/23/1997PPASS
Details
07/23/97 333 - review shaft requirements at pizza hut
INSP - Carpentry7/23/19977/22/19977/23/1997PPASS
Details
/ / 333 - met with Rich
INSP - Carpentry7/21/19977/21/19977/21/1997APART
Details
07/21/97 333 - pool resubmittal to Carl W
INSP - Framing/Rough-in7/21/19977/21/19977/21/1997APART
Details
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED 3rd floor
INSP - Framing/Rough-in7/18/19977/18/19977/18/1997APART
Details
/ / 333 - 3rd floor partial
INSP-Sprinkler Rough-in/Hydro7/17/19977/17/19977/17/1997AFAIL
DetailsJoe Tawney
walkthrough of floors 1-6 and penthouse for sprinkler locations and bracing. plans not available, bracing not complete, some obstructions noted, all areas not covered, porte coutre not covered
INSP - Carpentry7/11/19977/11/19977/11/1997 PART
Details
07/14/97 333 - reviewed floor sinks and firestoping in arena
INSP - Carpentry7/10/19977/10/19977/10/1997 PASS
Details
07/09/97 333 - second floor in progress of cover
INSP-Sprinkler Rough-in/Hydro7/7/19977/8/19977/8/1997APASS
DetailsJoe Tawney
07/08/97 406 - PLEASE GO OUT AT 10:00 UNITED WATER IS SCHEDULED AT THE S OK ON UNDERGROUND FLUSH
INSP - Carpentry7/6/19977/6/19977/6/1997 PASS
Details
07/06/97 333 - reviewed site
INSP - Carpentry7/2/19977/2/19977/2/1997 PASS
Details
/ / 333 - met with Jackie about shaft details gave resubmittal for 4th floor to plan review
INSP - Wall cover7/1/19977/1/19977/1/1997APART
Details
07/01/97 333 - second floor partial
INSP - Conference6/30/19976/27/19976/27/1997PPASS
Details
second floor
INSP - Conference6/27/19976/26/19976/26/1997PPASS
Details
met with Rich
INSP - Framing/Rough-in6/19/19976/19/19976/19/1997 FAIL
Details
06/18/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL
INSP - Framing/Rough-in6/19/19976/19/19976/19/1997 FAIL
Details
06/18/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL
INSP - Conference6/18/19976/17/19976/17/1997PPASS
Details
met with architect and owners about requirements for temp for arena only
INSP - Conference6/16/19976/16/19976/16/1997 PASS
Details
06/15/97 333 - 2nd floor dampers ok
INSP - Framing/Rough-in6/11/19976/11/19976/11/1997 PART
Details
/ / 333 - 2nd floor framing ok to cover all but shafts dampers not in need to look at floor closure at stair/elevator shaft
INSP - Conference6/10/19976/10/19976/9/1997PPASS
Details
06/10/97 333 - sent letter To John C
INSP - Framing/Rough-in6/9/19976/9/19976/9/1997PFAIL
Details
dampers not in
INSP - Framing/Rough-in6/4/19976/4/19976/4/1997 FAIL
Details
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in6/4/19976/4/19976/4/1997 FAIL
Details
06/04/97 333 - CN PLACED
INSP - Carpentry5/21/19975/21/19975/21/1997 PASS
Details
/ / 333 - met with Rich left letter for John
INSP - Conference5/11/19975/11/19975/11/1997 PASS
Details
/ / 333 - met with John Cunningham
INSP - Conference5/11/19975/11/19975/11/1997 PASS
Details
/ / 333 - met with Rich
INSP - Conference5/11/19975/11/19975/11/1997 PASS
Details
/ / 333 - reviewed submittal
INSP - Conference5/7/19975/7/19975/7/1997 PASS
Details
/ / 333 - worked on letter about dampers talked with ISI about 1 hr exterior walls
INSP - Conference5/7/19975/7/19975/6/1997PPASS
Details
05/07/97 333 - met with all subs about firestoping
INSP - Conference5/4/19975/4/19975/4/1997 PASS
Details
/ / 333 - reviewed firestoping with Bob
INSP - Conference4/30/19974/30/19974/30/1997 PASS
Details
/ / 333 - sent letter of transmittal to John
INSP - Conference4/28/19974/28/19974/28/1997 PASS
Details
/ / 333 - sent Letter Of Transmittal to John Cunningham
INSP - Conference4/27/19974/27/19974/27/1997 PASS
Details
/ / 333 - approved firestop method at efis panels at floor
INSP - Conference4/24/19974/24/19974/24/1997 PASS
Details
/ / 333 - sent letter of transmittal about firestop at floor lines
INSP - Conference4/20/19974/20/19974/20/1997 PASS
Details
/ / 333 - reviewed details with rich
INSP - Carpentry4/16/19974/16/19974/16/1997 PASS
Details
/ / 333 - in progress
INSP - Conference4/13/19974/13/19974/13/1997 PASS
Details
/ / 333 - MET WITH RICH FIRESTOPING AT WALL TO BEAM ATTACHMENT EXTERIOR WALLS OK
INSP - Conference4/7/19974/7/19974/6/1997APASS
Details
04/07/97 333 - talked to mti met with rich
INSP - Carpentry3/26/19973/26/19973/26/1997 PASS
Details
/ / 333 - framing in progress asked elect plumbing and mech for firestopping submittals
INSP - Carpentry3/24/19973/24/19973/24/1997 PASS
Details
/ / 333 - talked about wood cap at parapet
INSP - Conference3/24/19973/24/19973/23/1997PPASS
Details
03/24/97 333 - talked to elect , plumb , and mech about submittals for f looked at framing west and south walls need detail for top connection 1hr wall as asked for in transmittal of last week
INSP - Conference3/20/19973/20/19973/20/1997APASS
Details
checked west and south fire wraps on beams
INSP - Conference3/7/19973/7/19973/6/1997PPASS
Details
03/07/97 333 - sent letter of transmittal
INSP - Conference3/5/19973/6/19973/5/1997APASS
Details
03/06/97 333 - TALKED ABOUT FIREWALLS
INSP - Conference3/4/19973/5/19973/4/1997ACANC
Details
03/05/97 333 - resent for thursday
INSP - Framing/Rough-in2/19/19972/19/19972/18/1997PFAIL
Details
02/19/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED